Guide on the Use of the Changes Clause:
What Modifications Trigger Competition?
An Additional Help for ADS Chapter 302
New Edition Date: 03/29/2021
Responsible Office: M/OAA/E
File Name: 302sax_032921
1
Guide on the Use of the Changes Clause: What Modifications Trigger
Competition?
A Justification and Approval (J&A) is required for an existing award when a proposed
action triggers competition. Competition is not triggered by any action taken specifically
in accordance with a term and condition of the award. Competition may be required for
modifications of existing contracts that exceed the scope of the original contract by
adding new work through an increase to the total estimated cost (TEC) of the award, a
change to the Statement of Work (SOW), or an extension of the period of performance
(POP).
Every contract is unique. Each situation must be analyzed on its own facts and
circumstances, considering the magnitude and type of changes ordered within the
scope of the contract and their cumulative effect upon the contract as a whole.
Exercise of a priced option or an equitable price adjustment are examples of contract
actions that do not trigger competition. Other examples of the types of contract
modifications that generally do not trigger competition include the following:
Cost overrun - An increase in the TEC of a cost reimbursable contract in order
to allow the contractor to complete work already specified in the contract that
costs more than originally anticipated;
Delay - An extension to the POP granting the contractor additional time to
complete the deliverables specified in the existing SOW (Delays can be
“Excusable,” “Government-caused,” or “Contractor-caused,” or “concurrent,”
each of which have different contractual implications);
Changes - Changes within the general scope of the contract subject to the
applicable changes clause, FAR 52.243-1 through -5, that could have been
reasonably anticipated by the offerors; or
Any combination of these.
a. Cost Overruns
The contractor requires additional funding in order to complete the contract. Do I
need a J&A to increase the TEC?
If the CO needs to increase the TEC of a contract to allow the contractor to incur
additional costs not originally anticipated to complete work already within the scope of
the contract, the contract has a cost overrun. The CO has discretion to fund or not
fund an overrun.
In a Cost-Plus-Fixed-Fee (CPFF) completion type contract, FAR 16.306 states that “in
the event the work cannot be completed within the estimated cost, the Government
2
may require more effort without increase in fee, provided the Government increases
the estimated cost.” Under a CPFF term type contract, a cost overrun may generally
occur if the cost of labor exceeds what was anticipated and/or indirect costs are higher
than anticipated.
Funding a cost overrun does not require a J&A. Cost overruns are sometimes an
unavoidable risk of the cost-reimbursement type contract. While overruns are
occasionally caused by contractor waste or inefficiency, often they are due to the
unavoidable lack of certainty in contract requirements. Given the nature of the work
acquired by cost-reimbursement contracts, contractor performance often evolves in
ways neither the contractor nor the Government foresaw at the time of award.
Cost Overrun Examples:
1) A CPFF completion type contract is issued for a construction project for the
building of a road overseas. The host country government had promised to
facilitate the contractor in obtaining the necessary permits. The host
government experienced difficulty in its engagement with the local government
authorities. The contractor had to hire a local law firm to facilitate the permitting,
resulting in additional unanticipated costs.
Determination: The increased costs under this contract are not the result of new
work being added to it, so competition requirements are not triggered. In
accordance with FAR part 16.306(d)(1), in the event the work cannot be
completed within the estimated cost, the Government may require more effort
without increase in fee, provided the Government increases the estimated cost.
2) By year three of a CPFF term type contract, the contractor’s overhead rates had
increased by 20%. Additionally, the exchange rate changed from when the
contract was executed, costing significantly more money to perform the contract.
Determination: The increased costs under this contract are not the result of new
work being added to it, so unless the contract’s terms and conditions contained
a different agreement on exchange rate fluctuations or a ceiling on indirect
costs, competition requirements are not triggered. If the CO elects to increase
the TEC of the contract with no additional fee authorized, this action would not
require a J&A.
3) A 5-year CPFF completion contract for technical assistance to support the
Mission’s eight Government to Government (G2G) agreements required the
contractor to help manage the Mission’s portfolio of G2G awards and provide
capacity building services to the host country implementers. By the end of year
4, the G2G portfolio had grown to twelve agreements and the COR has directed
the contractor to take action with respect to all of them. The contractor informs
the CO that it will run out of funds in two months, but the contract period of
performance does not end for 10 months.
3
Determination: The addition of four new G2G agreements that the contractor
must provide oversight for, as well as the new host country partners, has
resulted in a cost increase. Although the contractor was performing essentially
the same work, the cost increase was a direct result of the additional
agreements it was required to help manage. This is not a cost overrun because
the additional cost resulted from work not contemplated in the original award.
b. Delays
Can my contract period of performance be extended due to a delay without a J&A?
If you need to extend the period of performance to allow the contractor to complete
work that is already specified in the contract, then you may not need a J&A. It is
important to understand the specific contract type and cause of the delay in order to
determine the appropriate action.
Excusable delays are defined as delays beyond the control of the contractor and
without the fault or negligence of the contractor. The Excusable Delay clause allows
the government to either revise the delivery schedule/period of performance or
terminate the contract for convenience.
Under a cost plus fixed-fee (CPFF) completion type contract, the contractor may
be given additional time to complete the deliverables specified in the existing
SOW. If there was an "excusable delay," then the authority to extend the period
of performance would be the excusable delay clause, FAR 52.249-14. If there
was no excusable or government caused delay, then the CO can terminate for
default or give the contractor additional time to complete the work in return for
some consideration.
Under a CPFF Term contract, the contract ends when the contractor provides
the agreed upon level of effort (LOE). The Excusable Delays clause would
allow for extension of the period of performance to allow the contractor to
provide the LOE included in the contract, but this clause does not allow for
additional LOE to be added to the contract.
Government-caused delays. If the government was the cause of the delay, it may be
required to extend the time for completion.
Contractor-caused delays. A delay the government has not authorized and for which
the contractor is at fault. The CO should negotiate consideration for the government
allowing performance to continue. The delay should be reflected in the contractor’s
Contractor Performance Assessment Reporting System (CPARS).
4
Concurrent delays. It is possible to have a delay, elements of which were caused by
both the contractor and the government.
Excusable Delays Example:
1) The completion of a CPFF completion contract was delayed due to security
incidents that occurred in the districts of the host country where the contract
activities were being implemented. The host country government restricted
access to the region while addressing the incidents. The contractor was
delayed in their performance because they were unable to access the region as
planned.
Determination: These delays were outside of the Contractor’s control. In this
case the FAR clause 52.249-14 Excusable Delays authorizes the CO to extend
the contract. The CO may extend the contract to adjust the period of
performance after analyzing the impact the delay had on the contract schedule.
2) A CPFF term contract called for the contractor to provide 5,000 days of labor
under the local technical assistance line item. During the last year of
performance, a global pandemic struck. Based on a contractor request, the
technical office asks the CO to use the excusable delay clause to extend the
contract and add LOE since performance was delayed and there are sufficient
funds on the contract.
Determination: The term form describes the scope of work in general terms and
obligates the contractor to devote a specified level of effort for a stated time
period. Under this form, if the performance is considered satisfactory by the
Government, the fixed fee is payable at the expiration of the agreed-upon
period, upon contractor statement that the level of effort specified in the contract
has been expended in performing the contract work. In accordance with FAR
16.306, “Renewal for further periods of performance is a new acquisition that
involves new cost and fee arrangements.” FAR 52.249-14, Excusable Delays,
which is to be included in all cost-reimbursement contracts, provides in
paragraph (c) that the relief granted to the contractor in this scenario is revision
to the "delivery schedule," not additional LOE. The CO may extend the period of
performance to allow the contractor to provide the LOE under contract, but may
not add additional LOE to the contract without a J&A.
Excusable Delays - Indefinite Delivery/Indefinite Quantity (IDIQs) and Task Orders
1) A Task Order's (TO’s) work is delayed when much of their staff are on ordered
departure or quarantined due to issues associated with the COVID-19 outbreak
in 2020. As a result, the CO wants to use the Excusable Delays clause to
extend the task order long enough to allow the contractor to complete the work.
5
Determination: The Excusable Delays clause can be used to extend a Task
Order. However, in addition to the requirements normally applicable to a stand-
alone contract, the CO must examine the IDIQ as well. The CO must confirm
that extending the task order will not cause the TO to go beyond the IDIQ's
period of performance (POP). If the extension does go beyond the POP end
date, then the IDIQ must also be extended. The IDIQ CO can also use the
Excusable Delays clause to extend the IDIQ's POP and then the Task Order CO
can extend the TO's POP.
2) An IDIQ's ordering period is expiring soon. Due to the COVID-19 outbreak in
2020, multiple orders were delayed because of shutdowns in operations,
quarantine actions, authorized departures, redesigning programs based on new
operating parameters as a result of the outbreak, and the need to calculate
increased costs associated with new operating measures (PPE, virtual
workspace, etc.). Can we use the Excusable Delays clause to extend the
ordering period?
Determination: No. Under an IDIQ, there is not any guarantee that the full order
amount (TEC) will be ordered collectively by the government. IDIQs create an
opportunity for COs to place orders in an expedited manner. The excusable
delays clause authorizes contractual remedies when a failure to perform was
outside of the control of the contractor. In this scenario, there is no existing
work on contract that requires additional time for performance. In most cases,
to extend the ordering period of an IDIQ, a CO will need to execute a J&A.
Please remember to submit that J&A to the justificationsanda@usaid.gov
mailbox for clearance by the ACA.
c. Changes
Are there any situations other than cost overruns and excusable delays in which the
CO can make non-administrative changes to the contract without triggering
competition?
There is a difference between a prospective out-of-scope contract modification
(cardinal change) that requires a J&A and a within-scope contract modification that
does not trigger the need to document use of noncompetitive authority. Generally, all
modifications must be within the overall scope of the contract. This principle applies in
the context of both competitive and non-competitive acquisitions.
In certain circumstances, changes to elements of a contract may be necessary to
achieve the results or deliverables of the contract. Changes that are within the general
scope of the contract can be made pursuant to the applicable Changes clause (FAR
52.243-1 through -5).
6
How does the CO determine whether a proposed change falls within the scope of the
Changes clause?
When considering whether a change is authorized under the Changes clause, each
case must be analyzed on its own facts and in light of its own circumstances. First, the
change must relate to one of the elements described in the clause itself (e.g., the
following elements are described in FAR 52.243-2 Changes-Cost-Reimbursement,
Alternate I for services):
(1) Description of services to be performed.
(2) Time of performance (i.e., hours of the day, days of the week, etc.).
(3) Place of performance of the services.
(4) Drawings, designs, or specifications when the supplies to be furnished are to be
specially manufactured for the Government in accordance with the drawings, designs,
or specifications.
(5) Method of shipment or packing of supplies.
(6) Place of delivery.
The CO must consider the magnitude and quality of the changes ordered and their
cumulative effect upon the contract as a whole. Contract modifications cannot
materially depart from the scope of the original procurement without a J&A. The
analysis with respect to scope is an objective one viewed from the perspective of
potential offerors for the original procurement, so the CO must examine the scope of
the proposed contract modification in comparison to the original solicitation.
The courts and GAO determine whether a change is within the scope of the contract by
examining if offerors should have reasonably anticipated this type of contract change
based upon the information that was available in the solicitation. If an offeror would not
have anticipated that type of change, then the modification would represent a cardinal
change and a J&A is required because the modification would prevent potential
offerors from participating in what should be a new procurement.
Changes Clause Examples:
1) A contract was awarded for civil society engagement in governance in a fragile
state. The solicitation had put offerors on notice that should armed conflict arise
in the target regions, the contractor may be required to identify new regions in
the country in which to focus their effort. As performance begins, insurgents
start a takeover of one of the regions in which the contractor is performing. The
CO directs the contractor to pull out of this region, to provide analysis on other
7
potential regions to target, and then has the contractor restart the interventions
in this new identified region.
Determination: Both the change in the additional place of performance as well
as the costs associated with the shutdown in one region (and set up in another),
can be included in the contract using the Changes Clause because these
changes are within the general scope of the contract, change in the place of
performance is covered by the clause, and the language in the solicitation put
offerors on notice that they should expect such a change.
2) The solicitation of an education contract included a line item for upgrade of the
educational facilities. After the award, less funding was received for the
program and so the contract was descoped to remove the upgrade of five
schools. Funding priorities subsequently changed and a modification was
proposed to rescope the contract and add the funding for the five schools back
into the contract.
Determination: The Changes Clause included in the contract can be properly
cited in the proposed modification, rescoping the contract (and adding back the
funds that were removed as part of the descoping) because the work was
included in the original solicitation.
3) A malaria program includes a combination of bed nets, spraying, etc. During
implementation of the program, a new mosquito spray that was previously
unavailable was approved for use in the country for the particular challenge. In
order to use the new technology, the CO modifies the contract to make the
necessary changes and cover the associated costs involved with the changes.
Determination: The Changes Clause can be properly cited for modification to
the contract since the original nature and purpose of the contract has not been
changed. The spray identified in the solicitation and contract was the only
spray in use at the time and offerors were not evaluated on the spray mixture.
The change in spray composition did not prejudice any of the offerors, all of
whom should have reasonably understood that if the approved spray in the host
county changed, the contract would need to be modified in order to achieve its
original purpose.
4) The Goat Sellers Activity was competitively awarded by a USAID Mission for five
years with a TEC of $11,880,000. The activity was designed to identify
interventions in goat products export supply chain from farm to dock. These
interventions were designed to improve the overall export of goat products by 10
percent from 2016 export levels. After award, the European Union (EU)
announced new certification requirements for all goat product imports. The EU
is the host country’s single largest goat product market. There are no certifying
officials in the host country, therefore, once the certification becomes
8
mandatory, the host country will be denied its most significant goat product
market if it cannot comply.
The best solution to meet the goals of the award is that the contractor begins
implementation of a train-the-trainers program at the host country’s College of
Agriculture to create a cadre of trainers for future certifying officials. Since the
activity is already embedded in the College of Agriculture, the ‘training of
trainers’ program can fit seamlessly into ongoing programming. In addition, the
contractor will provide enough certifying officials in the form of Short Term
Technical Assistance to allow for the continued export of goat products to the
EU for a 120-day period. Afterwards, sufficient local certifying staff will be
available having completed the College of Agriculture’s training program.
USAID estimates that the total increase in cost will be $915,000, which will be
added to the TEC in addition to these certification objectives.
Determination: The CO reviewed the solicitation and noted that as part of
increasing goat product exports, it stated the need to identify export market
requirements. Once identified, the contractor was expected to assist goat
product producers to introduce processes into the supply chain where needed to
meet those requirements. The CO determined that a reasonable person could
expect those requirements to apply to both existing and new markets. Also
requirements in an existing market might vary depending on the targeted market
area, i.e., animal, person, organic, grass fed, etc. It is reasonable to expect that
requirements might be fluid at times as regulatory changes take place. This is a
change that an offeror/contractor could reasonably have expected.
5) The Mission has a CPFF contract in place to provide access to technical
services, training, and capacity-building related to improving urban and local
governance. The technical team is seeking to modify the contract's scope of
work to make explicit the installation of street signs, lighting, and light
landscaping for municipal streets and city parks. The proposed activities are
estimated to cost approximately $600,000 over the remaining period of
performance (three years) of a $30 million contract. The activities fit very closely
with the sub-purposes of the SOW: improved service delivery, increased
responsiveness to citizens' priorities, and enhanced capacity to promote
community resilience. For instance, the installation of street lighting would have
a direct, immediate, and visible impact on improving the service delivery of
municipalities. Additionally, the contractor has conducted numerous surveys and
needs assessments of the municipalities for which it is providing technical
assistance: these activities have been identified as a priority of the citizens.
Will the CO add these activities to the SOW and include the required
construction clauses in the contract using the changes clause?
Determination: Despite the relatively small increase to the TEC that would
result from this action and the benefits it would provide to the program’s
objectives; this action would likely trigger competition requirements. It is clear
9
that the original solicitation and contract did not anticipate construction activities
under the award, since this is a technical assistance contract that did not
anticipate construction, as demonstrated by the SOW and the lack of any
construction clauses. Offerors would not have reasonably expected this
change.
Documenting the determination:
ADS 302.3.4.5(c) requires that the CO make a written determination that the change
does not trigger competition. This determination can be incorporated into the
modification negotiation memorandum or documented in a “stand-alone” specific
determination memorandum. A sample Determination Memo is located on the
M/OAA templates page.
The CO should consider the issues below in making and documenting the
determination:
Does the original contract, as modified, call for essentially the same
performance?
Does the solicitation or the initially awarded contract contain information that
would lead an offeror or contractor to reasonably anticipate the need for a
change of this nature?
Does the modification substantially change the type of product or service being
delivered or performed, the quantity of the product or service, the performance
period, and/or the cost between the original contract and modified contract?
Does the modification include additional time spent on performance of the
contract when such time is extended to add significantly more quantity or new
requirements to the contract?
302sax_032921