BY ORDER OF THE
SECRETARY OF THE AIR FORCE
DEPARTMENT OF THE AIR FORCE
INSTRUCTION 63-138
2 JANUARY 2024
Acquisition
ACQUISITION OF SERVICES
COMPLIANCE WITH THIS PUBLICATION IS MANDATORY
ACCESSIBILITY: This publication is available for downloading or ordering on the e-
Publishing website at www.e-publishing.af.mil.
RELEASABILITY: There are no releasability restrictions on this publication.
OPR: AFPEO/CM Certified by: AFPEO/CM
(Ms. Nancy K. Andrews)
Supersedes: AFI 63-138, 30 September 2019 Pages: 41
This publication implements Air Force Policy Directive (AFPD) 63-1/20-1, Integrated Life Cycle
Management, for the acquisition and management of contracted services within the Department of
the Air Force (DAF). It provides guidance and procedures to meet requirements and processes of
the Federal Acquisition Regulation (FAR), Defense FAR Supplement (DFARS), Department of
the Air Force FAR Supplement (DAFFARS) and Department of Defense Instruction (DoDI)
5000.74, Defense Acquisition of Services. This publication applies to civilian employees and
uniformed members of the United States Space Force, the Regular Air Force, and the Air Force
Reserve. It applies to the Air National Guard (ANG) when acquiring services through a DAF
Contracting Office. Applicability and exceptions to this DAFI are detailed in paragraph 1.2. It
applies to all activities who acquire services through a DAF Contracting Office or utilize funding
appropriated to the DAF to acquire services. This DAFI may be supplemented at any level, but all
supplements must be routed to the office of primary responsibility (OPR) of this publication for
coordination prior to certification and approval and may not restrict the acquisition flexibilities
contained within. Refer recommended changes and questions about this publication to the OPR
using the DAF Form 847, Recommendation for Change of Publication; route DAF Forms 847
from the field through the appropriate functional chain of command. Ensure all records generated
because of processes prescribed in this publication adhere to Air Force Instruction 33-322, Records
Management and Information Governance Program, and are disposed in accordance with the Air
Force Records Disposition Schedule, which is located in the Air Force Records Information
Management System. Any records generated from instructions of this DAFI may become a part of
the official contract file that has an established disposition schedule and is defined in FAR Part 4,
Administrative and Information Matters. The authorities to waive Wing/Delta/Unit level
2 DAFI63-138 2 JANUARY 2024
requirements in this publication are identified with a Tier number (T-0, T-1, T-2, T-3) following
the compliance statement. Refer to DAF Manual (DAFMAN) 90-161, Publishing Processes and
Procedures, Table A10.1, for a description of the authorities associated with the Tier numbers.
Submit requests for waivers through the chain of command to the appropriate Tier waiver approval
authority, or alternately, to the publication OPR for non-tiered compliance items. See paragraph
1.3.1 within this publication for further non-tiered waiver guidance.
SUMMARY OF CHANGES
This document has been revised and should be completely reviewed. Changes include updating
and clarifying implementation of DoDI 5000.74 resulting from changes to that DoD Instruction,
addressing organizational changes resulting from the creation of the United States Space Force
(USSF), changes to roles and responsibilities, and changes to reflect two DAF Service Acquisition
Executives (SAEs). Removed the term Headquarters Air Force (HAF). HAF now represents the
Headquarters of the Department of the Air Force which includes the Office of the Secretary of the
Air Force (known as the Secretariat), Air Staff, and the Office of the Chief of Space Operations
(known as the Space Staff). For clarity, the instruction uses the terms Secretariat, Air Staff, and
Space Staff to describe the three specific components within the HAF. Instructions for post-award
program management have been strengthened. Names and acronyms for two positions have been
changed to align with their roles and responsibilities more clearly; Services Designated Official
(SDO) is now Services Acquisition Decision Authority (SADA) and Functional Services Manager
(FSM) is now Services Acquisition Lead (SAL) (see paragraph 2.11.). A table has been added to
establish Program Manager (PM)/SAL certification/credentials by Services Category level (see
Table 2.3.). In Chapter 2, the SAEs specifically appoint the Air Force Program Executive Officer
for Combat and Mission Support (AFPEO/CM) as the Senior Services Manager (SSM). The titles
of Chapters 3 and 4 have been changed to reflect the full content and restructuring of those
chapters. Chapter 3 encompasses all information related to the requirements approval process.
Chapter 4 is structured to correlate with the Seven Steps to the Services Acquisition Process.
Chapter 5 clarifies policies for the organizational structures by creating separate governance
instructions for each structure. Chapter 6 updates policy on sharing of the Quality Assurance
Surveillance Plan with contractors and replaces references to the Contracting Officer
Representative Tracking (CORT) Tool with information on Procurement Integrated Enterprise
Environment (PIEE) with associated applications Joint Appointment Module (JAM) and
Surveillance and Performance Monitoring Module (SPM). Throughout the document,
requirements established in previous versions of this instruction have been clarified to increase
adherence.
Chapter 1OVERVIEW AND APPLICABILITY 5
1.1. Purpose..................................................................................................................... 5
1.2. Applicability ............................................................................................................ 5
1.3. Waivers. ................................................................................................................... 7
Chapter 2ROLES, RESPONSIBILITIES, AND AUTHORITIES 8
2.1. Overview. ................................................................................................................. 8
DAFI63-138 2 JANUARY 2024 3
2.2. Service Acquisition Executive (SAE). ..................................................................... 8
2.3. DAF Senior Services Manager (SSM). .................................................................... 8
2.4. AF Program Executive Officer for Combat and Mission Support (AFPEO/CM). .. 9
2.5. Services Acquisition Decision Authority (SADA). ................................................. 9
Table 2.1. United States Air Force (USAF) SADAs by S-CAT. .............................................. 11
Table 2.2. United States Space Force (USSF) SADAs by S-CAT. .......................................... 12
2.6. Services Advocate (SA). .......................................................................................... 13
2.7. The Systems Program Executive Officer/Technology Executive Officer (S-
PEO/TEO) shall: ...................................................................................................... 13
2.8. MAJCOM/FLDCOM/DRU/FOA (if delegated) CC/CD/CV/Executive Director
(CA), Deputy Under Secretary of the Air Force (Management) (SAF/MG) for
Secretariat and Air Staff, and Space Force Director of Staff (SF/DS) for Space
Staff shall: ................................................................................................................ 14
2.9. Requirements Approval Authority (RAA). .............................................................. 14
2.10. Multi-Functional Team (MFT). ............................................................................... 15
2.11. Program Manager (PM)/ Services Acquisition Lead (SAL). ................................... 15
Table 2.3. Certification Levels for PMs/SALs. ........................................................................ 17
2.12. Contracting Officer (CO). ........................................................................................ 18
2.13. Contracting Officer’s Representative (COR). .......................................................... 18
2.14. Chief Contracting Officer’s Representative (C-COR). ............................................ 18
2.15. COR Supervisor. ...................................................................................................... 19
2.16. Quality Assurance Program Coordinator (QAPC). .................................................. 19
Chapter 3REQUIREMENTS APPROVAL PROCESS 20
3.1. Overview. ................................................................................................................. 20
3.2. Requirement Identification. ..................................................................................... 20
Table 3.1. USAF Requirements Approval Authority. .............................................................. 21
Table 3.2. USSF Requirements Approval Authority. ............................................................... 22
3.3. Requirement Review and Documentation. .............................................................. 22
3.4. Other RAD Considerations. ..................................................................................... 23
3.5. Acquisitions with Different Execution and Funding Organizations. ....................... 24
3.6. Amended Requirements. .......................................................................................... 25
Chapter 4SERVICES ACQUISITION PROCESS 26
4.1. Overview. ................................................................................................................. 26
4.2. Acquisition Planning (Steps 1 and 2). ...................................................................... 26
4 DAFI63-138 2 JANUARY 2024
4.3. Market and Enterprise Research (Step 3). ............................................................... 27
4.4. Early Strategy and Issues Session (ESIS). ............................................................... 27
4.5. Requirements Definition (Step 4). ........................................................................... 27
4.6. Acquisition Strategy (Step 5). .................................................................................. 28
4.7. Execute Acquisition Strategy (Step 6). .................................................................... 29
4.8. Post-Award Performance Management (Step 7). .................................................... 29
Chapter 5GOVERNANCE ASSESSMENT 31
5.1. Governance Assessment. ......................................................................................... 31
5.2. Applicable to Secretariat, Air Staff, and Space Staff. .............................................. 31
5.3. Applicable to MAJCOMs, FLDCOMs, FOAs, and DRUs. ..................................... 31
5.4. Applicable to Systems PEOs/TEOs. ........................................................................ 32
5.5. Annual Summary. .................................................................................................... 32
Chapter 6QUALITY OVERSIGHT 33
6.1. Overview. ................................................................................................................. 33
6.2. Quality Assurance Surveillance Plan (QASP). ........................................................ 33
6.3. Actions to Address Substandard Services and Contractual Non-Conformities. ...... 34
Attachment 1GLOSSARY OF REFERENCES AND SUPPORTING INFORMATION 35
DAFI63-138 2 JANUARY 2024 5
Chapter 1
OVERVIEW AND APPLICABILITY
1.1. Purpose.
1.1.1. The purpose of this DAFI is to ensure DAF services acquisition programs are managed
effectively, efficiently, and timely to meet mission needs. This instruction seeks to encourage
synergy within the services acquisition community, which consists of Program
Managers/Services Acquisition Leads, contracting professionals, functional representatives,
contracting officer representatives, quality assurance program coordinators, financial
managers, small business professionals, requiring activity personnel, contract attorneys, and
any other stakeholder charged with any part of developing, executing, or monitoring a services
requirement from identification to contract close-out. A services acquisition program (hereafter
referred to as “program”) is a set of services requirements executed through one or more
contract actions, interagency agreements, and/or other types of acquisitions with a common
mission or objective.
1.1.2. Organizational entities employ requirements approval and acquisition approval
authorities based on their assigned delegations. Sections and tables within Chapters 2 and 3
are divided into these organizational structures to illustrate the instructions specific to each
entity. The organizational structures are the Secretariat, Air Staff, Office of the Chief of Space
Operations (Space Staff), Systems Program Executive Officer/Technology Executive Officer
(S-PEO/TEO), Major Command (MAJCOM), Field Command (FLDCOM), Field Operating
Agency (FOA), and Direct Reporting Unit (DRU).
1.1.3. Use this instruction in conjunction with DoDI 5000.74, Defense Acquisition of Services,
and Air Force Instruction (AFI) 63-101/20-101, Integrated Life Cycle Management, to ensure
successful acquisition of services.
1.1.4. The DAF implements the requirements of DoDI 5000.74 for a Services Requirements
Review Board (SRRB) process in an ongoing, comprehensive, and multi-faceted approach.
The DAF’s requirements approval process (see Chapter 3) addresses the SRRB elements of
mission need, strategic alignment, workforce analysis, relationship to other requirements,
projected cost of requirement, and contract and work functions (i.e., inherently governmental
functions). The DAF’s services acquisition process (see Chapter 4) employs both the Early
Strategy and Issues Session (ESIS) and the Acquisition Strategy Panel (ASP) to address the
SRRB elements of issues, risk, and prioritization. Additionally, the DAF’s governance
assessment process (see Chapter 5) provides a comprehensive annual review of both the
performance of individual programs and the effectiveness of organizations’ management and
oversight of services acquisitions. Finally, the DAF’s Quality Assurance oversight process (see
Chapter 6) addresses the SRRB element of metrics.
1.2. Applicability.
1.2.1. This instruction applies to all personal and non-personal services acquisitions executed
with DAF appropriations, with a total services acquisition program value, in current year
dollars, greater than or equal to the simplified acquisition threshold (SAT) as defined at FAR
2.101, Definitions, regardless of the contracting activity, except as exempted in paragraph
1.2.3.
6 DAFI63-138 2 JANUARY 2024
1.2.1.1. Programs funded by DAF organizations that are executed by non-DAF entities
shall comply with both this DAFI and AFI 65-118, Air Force Purchases Using Military
Interdepartmental Purchase Requests (MIPRS). (T-1)
1.2.1.2. Use total services acquisition program values when determining delegation
thresholds. (See para 1.1.1 for the description of a services acquisition program)
1.2.2. Programs funded by non-DAF entities that are executed by a DAF organization shall
comply with this instruction.
1.2.3. The following categories of services are exempt from adherence to this DAFI (unless
designated as a special interest). This DAFI does apply to Advisory and Assistance Services
(A&AS) contracts that support the otherwise exempt categories set forth in paragraphs 1.2.3.1
through 1.2.3.6 below.
1.2.3.1. Research & Development (as described in FAR 35, Research and Development
Contracting).
1.2.3.2. Federally Funded Research and Development Center (FFRDC) Research and
Development Laboratories identified in Table 1. of DoDI 5000.77, DoD Federally Funded
Research and Development Center (FFRDC) Program.
1.2.3.3. Construction, as defined in FAR Part 2.101 and as applicable to FAR Part 36,
Construction and Architect-Engineer Contracts. However, this DAFI does apply to routine
recurring maintenance of real property as defined in FAR 37.101, Definitions.
1.2.3.4. Architect-Engineer Services, as defined in FAR 2.101.
1.2.3.5. Utilities.
1.2.3.6. Foreign Military Sales (FMS), regardless of FMS funding source.
1.2.3.7. Emergency or urgent one-time repairs or maintenance, with supporting
documentation.
1.2.3.8. Classified, cryptologic, and intelligence projects/programs except to the extent
practical at the discretion and decision of the responsible senior officials and decision
authorities.
1.2.3.9. Acquisition of services in direct support of a contingency operation, a
humanitarian or peacekeeping operation, or an emergency as declared by the President (See
FAR 2.101). This exemption shall apply to the response and initial deployment phase but
shall terminate based on conditions on the ground and a determination by the SADA as
shown in Tables 2.1 and 2.2.
1.2.3.10. Services listed in FAR 37.502, Exclusions.
1.2.3.11. Services acquired under other pathways of the Adaptive Acquisition Framework
(see DoDI 5000.02, Operation of the Adaptive Acquisition Framework).
1.2.4. The following organizations are exempt from adherence to this DAFI:
1.2.4.1. Non-appropriated Fund Instrumentalities (unless using appropriated funds).
1.2.4.2. Air National Guard (ANG) (unless executing DAF funding).
DAFI63-138 2 JANUARY 2024 7
1.3. Waivers.
1.3.1. Unique situations may arise that necessitate deviation to the authority levels delineated
in Tables 2.1 and 2.2 and Tables 3.1 and 3.2. Changes to these authority levels require
approval by the SSM, except for S-PEO/TEO programs. Changes to S-PEO/TEO program
authority levels require approval by the S-PEO/TEO. For all other organizational structures,
submit changes to authority levels through the Services Advocate (SA) for staffing to the SSM.
1.3.2. Do not allow this instruction to impede the ability to respond rapidly to urgent
situations. Report, in writing to the SSM, any situation which requires a deviation from this
DAFI within 10 calendar days from the time the necessity for the deviation is identified or
understood.
8 DAFI63-138 2 JANUARY 2024
Chapter 2
ROLES, RESPONSIBILITIES, AND AUTHORITIES
2.1. Overview. The roles and responsibilities as described in this chapter may include further
delegations as defined within this DAFI or a Services Management Agreement (SMA). The SMA
documents specific roles and responsibilities of Secretariat, Air Staff, Space Staff, MAJCOM,
FLDCOM, FOA, and DRU organizations.
2.2. Service Acquisition Executive (SAE). The SAEs are the senior officials responsible for the
management of acquisition of contract services. The Assistant Secretary of the Air Force for
Acquisition, Technology, and Logistics (SAF/AQ) serves as the SAE of the DAF for non-space
systems, programs, and related activities. The Assistant Secretary of the Air Force for Space
Acquisition and Integration (SAF/SQ) serves as the SAE of the DAF for space systems, programs,
and related activities. The SAE is the Services Acquisition Decision Authority (SADA) with the
authority to assign responsibilities. Each SAE has delegated SADA authorities to AFPEO/CM
(except for programs assigned to S-PEOs/TEOs), who can further delegate those authorities. Each
SAE:
2.2.1. Assigns responsibility for the review and approval of procurements in each Services
Category (S-CAT). As SADA, the SAE holds acquisition planning and sourcing decision
authority for all services acquisitions greater than or equal to the SAT. The S-CATs are based
on dollar thresholds and establish the level of review, decision authority, and applicable
procedures in such categories.
2.2.2. Establishes policies, procedures, and guidelines.
2.2.3. Chairs annual Services Requirements Review (SRR) briefings presented by the S-
PEOs/TEOs under their authority.
2.3. DAF Senior Services Manager (SSM). Each SAE appoints AFPEO/CM as the DAF SSM.
The SSM is the acquisition expert responsible for assisting with planning, strategic sourcing,
execution, and management of services acquisitions. The SSM establishes, as appropriate,
management structures, acquisition governance, and processes to ensure effective implementation
of policies for the DAF on all services acquisitions. The SSM:
2.3.1. Serves as principal advisor to the SAEs for services acquisitions.
2.3.2. Informs, guides, and provides advice to the Secretariat, Air Staff, Space Staff, S-
PEOs/TEOs, MAJCOMs, FLDCOMs, FOAs, and DRUs to support their role regarding
management and oversight for services requirements within their respective portfolios.
2.3.3. Provides and maintains policies, procedures, and governance structure for the
management and oversight of services acquisitions; creates, updates, and maintains templates,
tools, and guides for use by authorities responsible for services acquisitions.
2.3.4. Prepares required Congressional and Office of the Secretary of Defense (OSD) reports.
Assists S-PEOs/TEOs (as requested) in addressing Congress on services acquisition elements
within their respective portfolios.
2.3.5. Performs enterprise-level data analysis on DAF services acquisitions.
DAFI63-138 2 JANUARY 2024 9
2.3.6. Manages and oversees the requirements approval process for services acquisitions, as
described in Chapter 3.
2.3.7. Facilitates training and development of the services acquisition workforce.
2.3.8. Acts as the DAF acquisition liaison to the non-traditional acquisition workforce
involved in services acquisitions and provides guidance appropriate for their training in
services acquisition procedures. Non-traditional acquisition workforce personnel are those
involved in an acquisition but do not occupy an acquisition-coded position or belong to an
acquisition related career field.
2.3.9. Fosters a services acquisition culture within the DAF using focused strategic messaging
through the conduct of periodic services acquisition seminars, as funding allows.
2.4. AF Program Executive Officer for Combat and Mission Support (AFPEO/CM). The
SAEs for the DAF assign SADA responsibility to AFPEO/CM for the management and execution
of services requirements not assigned to S-PEOs/TEOs. AFPEO/CM:
2.4.1. Executes SADA authority for services acquisitions as assigned by the SAE. Delegates
SADA authority to designated Secretariat, Air Staff, Space Staff, MAJCOM, FLDCOM, FOA,
and DRU senior leaders through this DAFI and as further detailed to the specific organization
through mutually agreed SMAs.
2.4.2. Establishes SMAs as necessary. The SMA is a written agreement between the
AFPEO/CM and the Commander or Director of the MAJCOM, FLDCOM, FOA, or DRU
organizations. SMAs for the Air Staff and the Space Staff are between the AFPEO/CM and
the respective Vice Chiefs. Secretariat organizations are included in the Air Staff SMA. The
SMA establishes the organization’s delegated authorities in keeping with their degree of
services acquisition maturity, continuous process improvement, workforce qualifications and
experience to manage services acquisitions, and in-place structure to support the management
and oversight of services acquisitions.
2.4.3. Reviews and coordinates documentation relating to services acquisitions prior to
submission to SAF/AQ or SAF/SQ.
2.4.4. Dedicates and prepares full-time Program Directors within the AFPEO/CM
organization who are responsible for coordinating services acquisitions and managing day-to-
day activities for assigned organizations. These personnel are liaisons who build relationships
between SADAs, their respective teams, and the SSM.
2.5. Services Acquisition Decision Authority (SADA). The SADA is the accountable senior
leader responsible for the execution, management, and oversight of services acquisitions in each
S-CAT identified in Tables 2.1 and 2.2 within their portfolio and/or expressed in an SMA. SADAs
may delegate all, some, or none of their SADA authorities, but still retain overall responsibility for
services acquisitions in their portfolio. The SADA shall:
2.5.1. Exercise authority for acquisition decisions including but not limited to:
2.5.1.1. The overall management and execution of services acquisitions, the degree of
services acquisition maturity, continuous process improvement, the workforce
qualifications and experience to manage services acquisitions, and the in-place structure to
support the management and oversight of services acquisitions.
10 DAFI63-138 2 JANUARY 2024
2.5.1.2. Source Selection Authority (SSA). Make the best value decision in a source
selection. See FAR 15.303(b), Responsibilities, DFARS 215.303(b)(2), Responsibilities,
DAFFARS Mandatory Procedure (MP) 5315.3, Source Selection, paragraph 1.4.1.2., and
Department of Defense Source Selection Procedures, paragraph 1.4.1.2.. Also applies to
FAR 16.505 Fair Opportunity decisions.
2.5.1.3. Acquisition Plan Approval Authority. Chair the Acquisition Strategy Panel.
Approve the acquisition plan. See FAR 7.1, Acquisition Plans, DFARS 207.1, and
DAFFARS 5307.1. For acquisitions under $50M, determine how the acquisition planning
will be documented.
2.5.1.4. Fee Determining Official. For Award Fee-type contracts, determine the amount of
award fee to be earned by a contractor for each award fee evaluation period after reviewing
Award Fee Board recommendations. See FAR 16.4, Incentive Contracts, DFARS 216.4,
and DAFFARS 5316.4.
2.5.2. Approve all non-performance-based services acquisitions greater than or equal to the
SAT and their related requirements documents, typically a Performance Work Statement
(PWS) and Quality Assurance Surveillance Plan (QASP). See DAFFARS 5337.170-2,
Approval Requirements.
2.5.3. Evaluate opportunities to meet category management and strategic sourcing objectives.
2.5.4. Ensure the formation and training of Multi-Functional Teams (MFTs) to execute the
Seven Steps to the Services Acquisition Process for their assigned program. (T-1) Verify
PM/SALs meet certifications/credentials listed in Table 2.3. Document PM/SAL assignment
as the MFT lead.
2.5.5. As the SSA, ensure source selection team members have the requisite acquisition
experience, skills, and training necessary to execute the source selection, and ensure the highest
level of team membership continuity for the duration of the selection process. (T-1)
2.5.6. Approve transfer of DAF appropriated funds to procuring activities outside of the DAF.
(See paragraph 4.2.3.)
2.5.7. Ensure development of a properly planned and resourced management approach for
monitoring contractor performance. (T-1) Confirm partnerships are established between the
requiring activity and the MFT with acquisition responsibility.
2.5.8. Ensure effective post-award management of cost, schedule, and performance. Attend
Program Management Reviews (PMRs) annually. (T-1) If unable to attend, review PMR
documentation at least annually. (See paragraph 4.8.2.9.)
2.5.9. Manage risk and assess the progress of the services acquisition against approved cost,
schedule, and performance metrics.
DAFI63-138 2 JANUARY 2024 11
Table 2.1. United States Air Force (USAF) SADAs by S-CAT.
S-CAT
Threshold
Pre-Award:
Rqmt Value
Post-Award:
Program
Value
(See Note: 6)
MAJCOM/FOA/DRU
Structure w/ a Signed SMA
(See Notes: 1,2,4,5,7)
Secretariat & Air
Staff Structure
w/ a Signed SMA
(See Notes:
1,2,4,5,7)
Systems PEO/TEO
Structure
(See Notes: 1,3,4)
S-CAT I
Est. total
value:
> $1 billion
($1B) or
> $300M in
any one year
AFPEO/CM
Delegable no lower than GO/SES
As designated by
USD(A&S),
SAF/AQ, or
AFPEO/CM
Delegable no lower
than GO/SES
S-PEO/TEO
Delegable no lower
than GO/SES
S-CAT I
I
Est. total
value:
> $250M but
< $1B
AFPEO/CM
Delegable no lower than GO/SES
AFPEO/CM
Delegable no lower
than GO/SES
S-PEO/TEO
Delegable no lower
than GO/SES
S-CAT II
I
Est. total
value:
> $100M but
< $250M
AFPEO/CM
Delegable no lower than GO/SES
AFPEO/CM
Delegable no lower
than GO/SES
S-PEO/TEO
Delegable no lower
than Senior Materiel
Leader (SML) or
O-6/GS-15 (or
equivalent)
S-CAT
IV
Est. total
value:
MAJCOM/FOA/DRU CC/CD/CV/CA
SAF/MG or
AFPEO/CM
S-PEO/TEO or
Deputy PEO/TEO
> $10M but
< $100M
Delegable to Wing/Directorate CC/CV or to a
grade no lower than O-6/GS-15 (or equivalent)
Delegable to no
lower than the 2-Ltr
Principal or Deputy
Delegable to no lower
than Materiel Leader
(ML)/ or O-5/GS-14
(or equivalent)
S-CAT V
Est. total
value:
> SAT but <
$10M
MAJCOM/FOA/DRU CC/CD/CV/CA
Delegable to Squadron CC/Division CC or to a
grade no lower than O-4/GS-13 (or equivalent)
> SAT but < $5M Delegable to an Acquisition
Workforce (AWF) Functional, as described in
DoDI 5000.66, with responsibility for the
management and oversight of the acquisition
SAF/MG or
AFPEO/CM
Delegable to no
lower than 3-Ltr
GO/SES
S-PEO/TEO or
Deputy PEO/TEO
Delegable no lower
than the Materiel
Leader (ML)/
or O-5/GS-14 (or
equivalent)
Notes:
1. Special Interest Items (any structure): The SADA is designated by the Under Secretary of Defense for Acquisition & Sustainment
(USD (A&S)) or designee. (See DoDI 5000.74, Table 1)
2. MAJCOM/FOA/DRU or Secretariat/Air Staff Structure w/SMA: SMAs may include delegations to specific positions or personnel
but will remain consistent with the delegation levels in this table. Delegations beyond this table require waiver by AFPEO/CM.
3. S-PEO/TEO Structure: Delegations beyond this table require waiver by the S-PEO/TEO. If assigned, the Milestone Decision Authority
(MDA) is the SADA. For S-CATs I&II, if S-PEO/TEO is O-6, delegable no lower than Deputy PEO/TEO.
4. Delegations expressly allowable within the table must be documented in writing and maintained by the parent organization.
5. For any Structure without an SMA, the SADA is the AFPEO/CM unless delegated in writing.
6. View related task orders within an ordering vehicle and/or options as one program for determining the appropriate threshold. (See para
1.1.1)
7. For acquisitions that support multiple MAJCOMs, Secretariat, and Air Staff organizations, the decision authority is the SADA of the
executing organization.
12 DAFI63-138 2 JANUARY 2024
Table 2.2. United States Space Force (USSF) SADAs by S-CAT.
S-CAT
Level
Threshold
Pre-Award: Rqmt Value
Post-Award:
Program Value
(See Note: 6)
FLDCOM Structure
w/ a Signed SMA
(See Notes: 1,2,4,5,7)
Space Staff Structure
w/ a Signed SMA
(See Notes: 1,2,4,5,7)
Systems PEO/TEO
Structure
(See Notes: 1,3,4)
S-CAT I
Est. total value:
> $1 billion ($1B) or
> $300M in any one year
AFPEO/CM
Delegable no lower than GO/SES
As designated by
USD(A&S),
SAF/SQ, or AFPEO/CM
Delegable no lower than
GO/SES
S-PEO/TEO
Delegable no lower
than GO/SES
S-CAT II
Est. total value:
> $250M but < $1B
AFPEO/CM
Delegable no lower than GO/SES
AFPEO/CM
Delegable no lower than
GO/SES
S-PEO/TEO
Delegable no lower
than GO/SES
S-CAT III
Est. total value:
> $100M but < $250M
AFPEO/CM
Delegable no lower than GO/SES
AFPEO/CM
Delegable no lower than
GO/SES
S-PEO/TEO
Delegable no lower
than the SML or
O-6/GS-15 (or
equivalent)
S-CAT IV
Est. total value:
FLDCOM CC/CD/CV/CA
SF/DS or AFPEO/CM
S-PEO/TEO or
Deputy PEO/TEO
> $10M but < $100M
Delegable to HQ Director, Delta CC, Space
Base Delta (SBD) CC/CV, SML/ML, or to
a grade no lower than O-6/GS-15 (or
equivalent)
Delegable to no lower
than the 2-Ltr Principal
or Deputy
Delegable to no
lower than the
Materiel Leader
(ML)/
or O-5/GS-14 (or
equivalent)
S-CAT V
Est. total value:
> SAT but < $10M
FLDCOM CC/CD/CV/CA
Delegable to Squadron CC/Division CC or
to a grade no lower than O-4/GS-13 (or
equivalent)
> SAT but < $5M Delegable to an
Acquisition Workforce (AWF) Functional,
as described in DoDI 5000.66, with
responsibility for the management and
oversight of the acquisition
SF/DS or AFPEO/CM
Delegable to no lower
than 3-Ltr Principal or
Deputy
S-PEO/TEO or
Deputy PEO/TEO
Delegable no lower
than the Materiel
Leader (ML)/
or O-5/GS-14 (or
equivalent)
Notes:
1. Special Interest Items (any structure): The SADA is designated by USD(A&S) or designee. (See DoDI 5000.74, Table 1)
2. FLDCOM or Space Staff Structure w/SMA: SMAs may include delegations to specific positions or personnel but will remain
consistent with the delegation levels in this table. Delegations beyond this table require waiver by AFPEO/CM.
3. S-PEO/TEO Structure: Delegations beyond this table require waiver by the S-PEO/TEO. If assigned, the Milestone Decision Authority
(MDA) is the SADA. For S-CATs I&II, if S-PEO/TEO is O-6, delegable no lower than Deputy PEO/TEO.
4. Delegations expressly allowable within the table must be documented in writing and maintained by the parent organization.
5. For any Structure without an SMA, the SADA is the AFPEO/CM unless delegated in writing.
6. View related task orders within an ordering vehicle and/or options as one effort for determining the appropriate threshold. (See para
1.1.1)
7. For acquisitions that support multiple FLDCOMs/Space Staff organizations, the decision authority is the SADA of the executing
organization.
DAFI63-138 2 JANUARY 2024 13
2.6. Services Advocate (SA). The SA is appointed by the Under Secretary of the Air Force
(USecAF), Vice Chief of Staff of the Air Force (VCSAF), Vice Chief of Space Operations
(VCSO), MAJCOM/CC, FLDCOM/CC, FOA/CC, or DRU/CC (SA appointing officials) to serve
as the direct representative of the services organization and act as a liaison to AFPEO/CM and the
SSM. The SA shall be a senior official within the relevant structure and hold the rank of General
Officer/Senior Executive Service (GO/SES) unless there is no other GO/SES within the
organization with direct access to the SA appointing official. In this case, the SA appointing
official may appoint the Deputy Commander (CD) or Vice Commander (CV) as the SA. The SMA
shall document the appointed SA. The SA shall:
2.6.1. Serve as the principal point of contact for services acquisitions within the Secretariat
and Air Staff, Space Staff, MAJCOM, FLDCOM, DRU, or FOA, as defined in their SMA.
2.6.2. Ensure their organization remains proactively engaged in improving the efficiency and
effectiveness of services acquisitions.
2.6.3. Facilitate submission of periodic reports and responses to data calls for service
acquisitions within their organizations.
2.6.4. Execute all roles and responsibilities as defined in their SMA.
2.6.5. Champion services acquisition workforce development and training.
2.7. The Systems Program Executive Officer/Technology Executive Officer (S-PEO/TEO)
shall:
2.7.1. Execute Services Acquisition Decision Authority (SADA) and Requirements Approval
Authority (RAA) for services acquisitions within their portfolio as outlined in Tables 2.1 and
2.2 and Tables 3.1 and 3.2.
2.7.2. Establish a management structure and processes for requirements review of all
acquisitions containing services greater than or equal to the SAT within the S-PEO/TEO’s
respective portfolio.
2.7.3. Create an annual SRR that reports budget, cost, schedule, performance, issues, and risks
of all services programs greater than or equal to $10M in the S-PEO/TEO’s portfolio. The SRR
shall be briefed to the cognizant SAE. Use the template provided on the AFPEO/CM
SharePoint website. (see References in Attachment 1)
2.7.4. Ensure programs are resourced with properly trained personnel. Personnel assigned to
work services acquisition elements should be trained on the Seven Steps to the Services
Acquisition Process. See available training on the AFPEO/CM SharePoint website. (see
References in Attachment 1)
2.7.5. Assign a Defense Acquisition Workforce Improvement Act (DAWIA) certified PM for
all services acquisitions greater than or equal to $100M. Organizations must gain AFPEO/CM
approval to waive this requirement. (See paragraph 2.11 and Table 2.3.)
2.7.6. Evaluate opportunities to meet category management and strategic sourcing objectives.
2.7.7. Establish an adequately planned and resourced management approach to monitor
contractor performance including quality assurance surveillance and services deliverable
tracking procedures. Ensure the building of required partnerships within the MFT are
established to execute services acquisitions.
14 DAFI63-138 2 JANUARY 2024
2.7.8. Ensure membership of an MFT is tailored (i.e., experience, quantity, etc.) for the size
and complexities of the services acquisition and members are appointed for all services
requirements greater than or equal to the SAT. The responsibilities of the MFT are defined in
paragraph 2.10.
2.8. MAJCOM/FLDCOM/DRU/FOA (if delegated) CC/CD/CV/Executive Director (CA),
Deputy Under Secretary of the Air Force (Management) (SAF/MG) for Secretariat and Air
Staff, and Space Force Director of Staff (SF/DS) for Space Staff shall:
2.8.1. Execute Services Acquisition Decision Authority (SADA) and Requirements Approval
Authority (RAA) for services acquisitions within their portfolio as outlined in Table 2.1. or
Table 2.2 for SADA and Table 3.1. or Table 3.2 for RAA.
2.8.2. Establish an SMA with AFPEO/CM. (See paragraph 2.4.4.) For MAJCOMs,
FLDCOMs, DRUs, and FOAs the SMA signatory is the CC. For Secretariat/Air Staff, the SMA
signatories are the USecAF and VCSAF; for Space Staff, the SMA signatory is the VCSO.
2.8.3. Establish a management structure and processes for all acquisitions containing services
greater than or equal to the SAT. (see paragraph 1.1.4.)
2.8.4. Ensure program Annual Execution Reviews (AERs) and an overall Effectiveness
Review for the organization are presented to AFPEO/CM on an annual basis. The
organizational SADA identified in the SMA (top level) may delegate the chair of these reviews
to no lower than the SA. (See Chapter 5)
2.8.5. Ensure adequate internal governance policies and procedures are in place to evaluate
services acquisitions above the SAT.
2.8.6. Assign a DAWIA certified PM for all services acquisitions greater than or equal to
$100M. Organizations must gain AFPEO/CM approval to waive this requirement. (See
paragraph 2.11 and Table 2.3.)
2.8.7. Ensure personnel assigned to work services acquisition elements within their programs
are properly resourced and trained on the services acquisition life cycle from requirements
generation through contract closeout.
2.8.8. Evaluate opportunities to meet category management and strategic sourcing objectives.
2.8.9. Establish an adequately planned and resourced management approach to monitor
contractor performance including quality assurance surveillance and services deliverable
tracking procedures. Ensure the building of required partnerships within the MFT are
established to execute services acquisitions.
2.8.10. Ensure membership of an MFT is tailored (i.e., experience, quantity, etc.) for the size
and complexities of the services acquisition and members are appointed for all services
requirements greater than or equal to the SAT. The responsibilities of the MFT are defined in
paragraph 2.10.
2.9. Requirements Approval Authority (RAA). The RAA approves services requirements at
Secretariat, Air Staff, Space Staff, MAJCOM, FLDCOM, FOA, DRU, and S-PEO/TEO levels.
For the purposes of DAF, the RAA fulfills the SRRB chair role as defined in DoDI 5000.74. The
RAA establishes a process that incorporates cross-functional representation from requiring
activity, contracting, financial management, and other pertinent organizations to identify, assess,
DAFI63-138 2 JANUARY 2024 15
validate, and approve services requirements. The approval of a requirement allows senior mission
leaders to prioritize mission requirements to best support their mission needs within available
funding limits. Tables 3.1 and 3.2 specify the authority levels. (Note: In some cases, the RAA and
the SADA may be the same person). The RAA shall:
2.9.1. Review and approve all Requirements Approval Documents (RADs) greater than or
equal to the SAT prior to approval of the acquisition strategy for the services being acquired.
2.9.2. Ensure all approved RADs that contain depot maintenance requirements are consistent
with their respective Depot Source of Repair decisions. (See AFMAN 63-122, Depot Source
of Repair Planning and Activation, 21 January 2020)
2.10. Multi-Functional Team (MFT).
2.10.1. The MFT is a mission-focused team responsible for developing contract requirements,
assessing contractor performance, and managing service delivery. The emphasis of the MFT
is on teamwork, trust, knowledge-sharing, and efficient execution. The MFT is responsible for
duties in each of the Seven Steps to the Services Acquisition Process outlined in the
Acquisition of Services pathway (see DoDI 5000.74).
2.10.2. This team includes representatives of all the stakeholders involved in the effort. Tailor
the membership of the MFT to fit the size and complexities of the acquisition. The MFT will
include the Program Manager (PM) or Services Acquisition Lead (SAL), Requiring Activity
Representative, Contracting Officer (CO), and Contracting Officer’s Representative (COR)
when assigned or designated. Others should be added to the MFT based on the pre- and post-
award specifics of the program; these include functional/technical subject matter experts, price
analyst, contract specialist, labor advisor, safety representative, logistics representative, and/or
Defense Contract Management Agency (DCMA) representative. Some members may be
necessary for their contribution to specific documents or tasks; these include the Quality
Assurance Program Coordinator (QAPC), legal advisor, security representative, cybersecurity
representative, finance representative, COR supervisor, functional commander/director, and/or
small business representative.
2.10.3. The SADA ensures the formation of the MFT. The MFT is led by a PM or by a SAL;
if by a SAL, with close coordination and assistance from the CO. Members of the MFT are
accountable to the PM/SAL for the activities related to each member’s functional area. (See
Chapter 4 and the MFT Resources Guide on the AFPEO/CM SharePoint website for
additional information).
2.11. Program Manager (PM)/ Services Acquisition Lead (SAL). The PM or SAL is the
designated individual with the responsibility and authority for managing cost, schedule,
performance, and risk of services acquisitions. The Department of the Air Force distinguishes
between DAWIA-certified acquisition PMs and functionals performing the duties of a PM. The
term Program Manager or PM, as used in this DAFI, refers to a DAWIA-certified PM. A DAWIA-
certified PM is required for Programs greater than or equal to $100M. (T-1) PMs may be appointed
within the grace period to meet certification required by their position as described in DoDI
5000.66, Defense Acquisition Workforce Education, Training, Experience, and Career
Development Program, para 5.1..f. The term SAL describes functionals (i.e., personnel from the
requiring activity) who perform the duties of a PM. A SAL (or PM if assigned by the SADA) is
required for all services acquisitions greater than or equal to the SAT and less than $100M. (T-1)
16 DAFI63-138 2 JANUARY 2024
Table 2.3 establishes certification and credential requirements for PMs and SALs. The PM or the
SAL performs the duties of the Functional Services Manager (FSM) as defined in DoDI 5000.74.
The PM or SAL:
2.11.1. Leads the MFT through the Seven Steps to the Services Acquisition Process. Tailors
program strategies and oversight. Recommends content, timing, and scope of decision reviews
and decision levels based on the characteristics of the capability being acquired (including
complexity, risk, and urgency) to satisfy user requirements.
2.11.2. Ensures MFT composition is adequately resourced relative to the scope and
complexity of the program considering management of the acquisition (policy and law),
business (financial and contract), technical (engineering, logistics, manufacturing, IT, etc.),
and leadership.
2.11.3. Develops and coordinates an MFT charter for S-CAT I III programs for signature by
all MFT members. MFT charters are recommended for S-CAT IV V programs. (T-1) The
MFT charter assigns resources and establishes roles and responsibilities of members. The MFT
charter also documents the acquisition objectives, schedule, deliverables, and communication
plan. Issues with development or execution of the charter shall be raised to the SADA for
resolution.
2.11.4. Translates program objectives into outcome-based services requirements with
measurable performance objectives and program metrics to measure success. Ensures program
objectives and goals are aligned with those of the leadership chain and the mission. Ensures
mission essential functions identified by the requiring activity are included in acquisition
planning and requirements documents. (see DFARS 237.76, Continuation of Essential
Contractor Services)
2.11.5. Utilizes appropriate program and project management tools, techniques, and business
processes to manage cost, schedule, and performance and associated issues, risks, and
opportunities.
2.11.6. Leads the MFT, seeks input, collaborates, and coordinates with team members to
develop necessary acquisition documents and artifacts to enable data-driven decisions for
effective execution. All members of the MFT must work in concert to ensure execution of
sound acquisition strategies and consistent administration of services programs.
2.11.7. Leads the MFT through the performance of market research and analysis of strategies,
best practices, and effectiveness of historical methods used to meet Government requirements.
2.11.8. Complies with all applicable regulatory and statutory requirements to include
developing and maintaining appropriate programmatic documentation.
2.11.9. Develops tailored and executable program strategies which consider the program’s
risk.
2.11.10. Proposes waivers and deviations as needed to streamline, tailor, and execute the
assigned program.
2.11.11. Leads the development of the acquisition strategy and ensures an ASP is conducted
for all acquisitions that require a written acquisition plan (AP) (See DFARS 207.103, Agency-
head Responsibilities, and DAFFARS 5307.104-92, Acquisition Strategy Panels (ASP) and AP
Approval Authority.
DAFI63-138 2 JANUARY 2024 17
2.11.12. Actively manages risks, issues, and opportunities from identification to resolution
using a documented risk management plan throughout the lifecycle of the program.
2.11.13. Defines processes for managing, prioritizing, and coordinating actions which may
impact requirements, cost, schedule, performance, risks, issues, and opportunities throughout
the lifecycle of the acquisition. Ensures any proposed changes or modifications are coordinated
with the MFT.
2.11.14. Develops a plan to effectively execute the approved program budget to include the
management of budget cuts, requirement growth, and contract underruns/overruns. Analyzes
funding risk and develops courses of action where disconnects exist between valid
requirements and available program funding. Actively engages in all activities related to
program funding.
2.11.15. Leads the development, implementation, and execution of award fee and other
incentive arrangements.
2.11.16. Ensures contractor performance is assessed using the QASP throughout the
acquisition lifecycle and the MFT takes appropriate action as required. (T-0)
2.11.17. Ensures a Contractor Performance Assessment Report (CPAR) is submitted annually
following guidance found in the General Services Administration Contractor Performance
Assessment Reporting System (CPARS) Guidance document. (T-0) PMs/SALs may serve as
the Assessing Official (AO).
2.11.18. Executes Program Management Reviews (PMRs). (See paragraph 4.8.2.9.)
2.11.19. Briefs program(s) at the AER to AFPEO/CM. (See Chapter 5)
2.11.20. Collaborates with the contracting officer and contractor to ensure contract closeout is
accomplished in a timely manner.
Table 2.3. Certification Levels for PMs/SALs.
Role
Program Value
Certification/Credential
S-CAT I*
Program Manager
Est > $1B or > $300M in any
one year
DAWIA PM Advanced Certification
S-CAT II
Program Manager
Est. total value:
> $250M but < $1B
DAWIA PM Practitioner Certification
S-CAT III
Program Manager
Est. total value:
> $100M but < $250M
DAWIA PM Practitioner Certification
S-CAT IV
Services Acquisition Lead
Est. total value:
> $10M but < $100M
Defense Acquisition University (DAU) Services
Acquisition Team Member Credential
S-CAT V
Services Acquisition Lead
Est. total value:
> SAT but < $10M
DAU Services Acquisition Team Member Credential
Notes:
1. Personnel appointed as PMs, as required by this table, must occupy an Acquisition Position Category billet, coded “A” (Program Manager) within the
Manpower Programming and Execution System (MPES). (T-1)
2. SADAs may appoint DAWIA-certified Program Managers to S-CAT IV and V requirements based on risk, complexity, and availability.
3. SALs should achieve credential NLT six months after designation.
4. Visit dau.edu for current Certification and Services Acquisition Team Member credentialing requirements.
18 DAFI63-138 2 JANUARY 2024
2.12. Contracting Officer (CO). The CO is the only person with the authority to obligate the
Government and direct a contractor’s performance. The CO carries out the requirements identified
in the Federal Acquisition Regulation (FAR) and its supplements.
2.12.1. The CO plans, awards, administers, modifies, interprets, takes corrective action, and
terminates a contract on behalf of the Government commensurate with the limitations specified
on the CO’s warrant.
2.12.2. As described in DoDI 5000.72, DoD Standard for Contracting Officer’s
Representative (COR) Certification, Enclosure 3, para 1(c), when applicable, the CO
designates a properly trained COR in writing. (T-0) COs shall designate a COR for all services
contracts, unless certain conditions are met, as described in DFARS Procedures, Guidance,
and Information (PGI) 201.602-2(d)(v)(A), Responsibilities. (T-0) Contracting Officers may
consider designating alternate CORs as required. COs are responsible for ensuring contract-
specific training is scheduled and provided. Training may be conducted by the CO, Contracting
Specialist, or QAPC. See DAFFARS MP 5301.602-2(d), Designation, Assignment, and
Responsibilities of a Contracting Officers Representative (COR), paragraph 1.3.
2.12.3. For acquisitions under $50M, the CO documents acquisition planning consistent with
SADA instructions.
2.13. Contracting Officer’s Representative (COR). CORs are nominated by the requiring
activity and, upon contract award, designated by the Contracting Officer. Requiring activities
should nominate CORs early in the acquisition process to allow the prospective COR to receive
required training and to provide timely input before contract award.
2.13.1. A COR executes the duties and responsibilities detailed in FAR 1.604, Contracting
Officer’s Representative (COR), DFARS PGI 201.602, DAFFARS Mandatory Procedure (MP)
5301.602-2(d), and DoDI 5000.72. (T-0) Specific duties are outlined in the Contracting
Officer’s COR designation letter.
2.13.2. Prospective CORs shall participate, as appropriate, in pre-award requirements
definition, acquisition planning, and contract formation processes (i.e., market research,
independent government estimate, justification and approval documentation). (T-3)
2.13.3. CORs may utilize subject matter experts (SMEs) to provide additional insight and
observations to the COR regarding the contractor’s performance. CORs must verify and
document the observations provided by SMEs; however, CORs shall not appoint, designate,
re-designate or sub-designate COR duties/responsibilities to other persons. (T-0)
2.13.4. CORs will use the Procurement Integrated Enterprise Environment (PIEE) system to
maintain documentation of COR training, surveillance activities, and approve contract
payments. See the DoD COR Guidebook for additional COR guidance. (T-0)
2.14. Chief Contracting Officer’s Representative (C-COR). When a CO or PM/SAL
determines that a services contract requires more than one COR, the requiring activity may
nominate, and the contracting officer may designate a C-COR. In addition to the COR
responsibilities identified in paragraph 2.13, the C-COR manages the activities of all CORs and
COR Supervisors for a particular contract to ensure compliance with regulatory, quality assurance
and reporting requirements specified in paragraphs 2.13 and 2.15.
DAFI63-138 2 JANUARY 2024 19
2.15. COR Supervisor. The COR Supervisor shall ensure subordinates fully accomplish their
COR duties, document the performance of those duties in the COR’s annual appraisal, and ensure
CORs are resourced with the time and materials needed. The COR Supervisor is responsible for
ensuring that subordinates utilize the Procurement Integrated Enterprise Environment (PIEE)
system to maintain documentation of surveillance activities and approve contract payments. See
FAR 1.604, DFARS PGI 201.602, DAFFARS MP 5301.602-2(d), and DoDI 5000.72 for duties
and responsibilities.
2.16. Quality Assurance Program Coordinator (QAPC). The QAPC is responsible for the
coordination and management of the organization’s contract quality assurance program.
2.16.1. The QAPC:
2.16.1.1. Trains CORs and COR supervisors on quality assurance procedures and verifies
COR training is accomplished. May conduct contract-specific training when necessary.
2.16.1.2. Monitors COR nominations, designations, terminations, and training records.
2.16.1.3. Assists in market research and PWS development with the MFT.
2.16.1.4. Assists with the integration of quality requirements into the contract, QASP, and
Award Fee/Incentive Plan as applicable.
2.16.2. Refer to DoDI 5000.72, DAFFARS MP 5301.602-2(d), and DAFFARS MP 5346.103,
Contracting Office Responsibilities, for additional QAPC responsibilities.
2.16.3. Refer to the MFT Resources Guide on the AFPEO/CM SharePoint site (see
References in Attachment 1) for more information related to the QAPC’s role on the MFT.
20 DAFI63-138 2 JANUARY 2024
Chapter 3
REQUIREMENTS APPROVAL PROCESS
3.1. Overview. Congressional and DoD direction dictates every services requirement greater
than or equal to the SAT be validated. DAF-funded requirements are validated and approved by
the Requirements Approval Authority (RAA). The RAA establishes a process that incorporates
cross-functional representation from the requiring, contracting, and financial management
communities to identify, assess, validate, and approve services requirements. A requirements
review process is critical to the final cost, schedule, and performance of an acquired service and
should incorporate current and accurate mission needs, spend data analysis, cost analysis, risk
analysis, and initial market research. The RAA ensures that services requirements are defined and
validated in a manner that promotes the most effective use of resources across the DAF enterprise.
See paragraph 1.1.4 for a full explanation of how the DAF implements the requirement for an
SRRB.
3.2. Requirement Identification. The requiring activity representative, or assigned PM/SAL,
documents the need for the proposed requirement and obtains requirements approval from the
appropriate RAA (see Tables 3.1 and 3.2) as soon as new requirements, follow-on requirements,
or changes to recurring requirements are identified.
3.2.1. If there are multiple requiring activities, follow AFI 25-201, Intra-Service, Intra-
Agency, and Inter-Agency Support Agreement Procedures, to execute a Memorandum of
Agreement (MOA) which identifies the requiring activities, the lead organization, PM/SAL
assigned, and RAA for execution of the acquisition. If the combined requirements total $100M
or more, the identified lead organization will provide the MOA to the SSM if requested.
3.2.2. When the organization determines a need for contracted services, the RAA, as described
in Section 2.9 and Tables 3.1 and 3.2, approves the requirement via the Requirements
Approval Document (RAD) prior to approval of the acquisition strategy. This process aligns
accountability and responsibility of the services requirement within the requiring activity’s
chain of command. The SADA, through written communication with the RAA, may grant a
waiver to extend the RAD approval timeline beyond the approval of the acquisition strategy.
Acquisition teams must explain the extenuating circumstances that require late approval in the
acquisition strategy documentation. However, the RAD shall be approved prior to the release
of the solicitation. (T-1) Exception: S-PEO/TEO (T-3)
3.2.3. For S-PEO/TEO programs of record, requirements approval is captured within the
mandatory milestone decision documents. The RAA is the assigned Milestone Decision
Authority (MDA). Clearly written services requirements vetted by the appropriate stakeholders
early in the life cycle or requirements included in the Acquisition Strategy or Life Cycle
Sustainment Plan serve as the requirements approval for services. For those services not
included in the original documentation, an amendment to the milestone documentation or a
separate RAD is required.
DAFI63-138 2 JANUARY 2024 21
Table 3.1. USAF Requirements Approval Authority.
Services
Category
(S-CAT)
Requirement
Value
MAJCOM/DRU/FOA
Structure
(Notes: 1,4,5)
Secretariat & Air Staff
Structure
(Notes: 1,2)
System PEO/TEO
Structure
(Notes: 1,3)
Special Interest
As designated by USD(A&S),
SAF/AQ, or AFPEO/CM
(all dollar values)
As designated by
USD(A&S), SAF/AQ, or
AFPEO/CM
(all dollar values)
As designated by
USD(A&S), SAF/AQ, or
AFPEO/CM
(all dollar values)
S-CAT I
Est. total value:
> $1B or
> $300M in any one year
MAJCOM/DRU/FOA
CC/CD/CV/CA
(delegable)
SAF/MG
S-PEO/TEO
(delegable)
S-CAT II
Est. total value:
> $250M but < $1B
MAJCOM/DRU/FOA
CC/CD/CV/CA
(delegable)
SAF/MG
S-PEO/TEO
(delegable)
S-CAT III
Est. total value:
> $100M but < $250M
MAJCOM/DRU/FOA
CC/CD/CV/CA
(delegable)
SAF/MG
S-PEO/TEO
(delegable)
S-CAT IV
Est. total value:
> $10M but < $100M
MAJCOM/DRU/FOA
CC/CD/CV/CA
(delegable)
SAF/MG
(delegable)
S-PEO/TEO or Deputy
(delegable)
S-CAT V
Est. total value:
> SAT but < $10M
MAJCOM/DRU/FOA
CC/CD/CV/CA
(delegable)
SAF/MG
(delegable)
S-PEO/TEO or Deputy
(delegable)
Notes:
1. RAD format is at the discretion of the RAA for all dollar values. All requirements greater than or equal to the SAT require an approved
RAD signed by the RAA indicated by dollar threshold in the above table (or as delegated). The RAA must show the existence of a
requirements review process.
2. Secretariat/Air Staff Structure: S-CAT IV and S-CAT V delegable to no lower than 3-Ltr Principal or Deputy. For SAF/CDM efforts,
the RAA is Administrative Assistant to the Secretary of the Air Force (SAF/AA) (delegable).
3. Systems PEO/TEO Structure: RAA for S-CAT I and II is the S-PEO/TEO, delegable to no lower than GO/SES or Deputy PEO/TEO
if S-PEO/TEO is O-6.
-RAA for S-CAT III is the S-PEO/TEO delegable to no lower than SML, O-6/GS-15 (or equivalent).
-RAA for S-CAT IV and V is either the S-PEO/TEO or Deputy delegable to no lower than the ML, O-5/GS-14 (or equivalent). In special
circumstances, the S-PEO/TEO may waive the grade requirement if the RAA has appropriate access to the S-PEO/TEO, or a GO/SES
within their leadership structure. Regardless of delegation level, if program has an assigned MDA, the MDA is the RAA.
4. MAJCOM/FOA/DRU Structure: MAJCOM/FOA/DRU CC/CD/CV/CAs may delegate authority for
S-CAT I, II, or III to a General Officer (GO)/Senior Executive Service (SES) within its command.
-S-CAT IV authority is delegable to Wing/Directorate CC or to a grade no lower than O-6/GS-15 (or equivalent).
-S-CAT V authority is delegable to Squadron CC or to a grade no lower than O-4/GS-13 (or equivalent).
5. Delegations to FOAs are not automatic but are at the discretion of their parent organization.
22 DAFI63-138 2 JANUARY 2024
Table 3.2. USSF Requirements Approval Authority.
Services
Category
(S-CAT)
Requirement
Value
FLDCOM Structure
(Notes: 1,3,5)
Space Staff Structure
(Notes: 1,2,5)
System PEO/TEO
Structure
(Notes: 1,4,5)
Special Interest
As designated by USD(A&S),
SAF/SQ, or AFPEO/CM
(all dollar values)
As designated by USD(A&S),
SAF/SQ, or AFPEO/CM
(all dollar values)
As designated by USD(A&S),
SAF/SQ, or AFPEO/CM
(all dollar values)
S-CAT I
Est. total value:
> $1B or
> $300M in any one year
FLDCOM CC/CD/CV/CA
(delegable)
SF/DS
S-PEO/TEO
(delegable)
S-CAT II
Est. total value:
> $250M but < $1B
FLDCOM CC/CD/CV/CA
(delegable)
SF/DS
S-PEO/TEO
(delegable)
S-CAT III
Est. total value:
> $100M but < $250M
FLDCOM CC/CD/CV/CA
(delegable)
SF/DS
S-PEO/TEO
(delegable)
S-CAT IV
Est. total value:
> $10M but < $100M
FLDCOM CC/CD/CV/CA
(delegable)
SF/DS (delegable)
S-PEO/TEO or Deputy
(delegable)
S-CAT V
Est. total value:
> SAT but < $10M
FLDCOM CC/CD/CV/CA
(delegable)
SF/DS (delegable)
S-PEO/TEO or Deputy
(delegable)
Notes:
1. RAD format is at the discretion of the RAA for all dollar values. All requirements greater than or equal to the SAT require an approved
RAD signed by the RAA indicated by dollar threshold in the above table (or as delegated). The RAA must show the existence of a
requirements review process.
2. Space Staff Structure: S-CAT IV and S-CAT V delegable to no lower than 3-Ltr Principal or Deputy.
3. FLDCOM Structure: FLDCOM CC/CD/CV/CAs may delegate authority for S-CAT I, II, or III to a General Officer (GO)/Senior
Executive Service (SES) within its command.
-S-CAT IV authority is delegable to HQ Directors, Delta CC, and Space Base Delta (SBD) CC/CV, or to a grade no lower than O-6/GS-15
(or equivalent).
-S-CAT V authority is delegable to Squadron CC, or to a grade no lower than O-4/GS-13 (or equivalent).
4. Systems PEO/TEO Structure: RAA for S-CAT I and II is the S-PEO/TEO, delegable to no lower than GO/SES or Deputy PEO/TEO if
S-PEO/TEO is O-6.
-RAA for S-CAT III is the S-PEO/TEO delegable to no lower than SML, O-6/GS-15 (or equivalent).
-RAA for S-CAT IV and V is either the S-PEO/TEO or Deputy delegable to no lower than the ML, O-5/GS-14 (or equivalent). In special
circumstances, the S-PEO/TEO may waive the grade requirement if the RAA has appropriate access to the S-PEO/TEO, or a GO/SES within
their leadership structure. Regardless of delegation level, if program has an assigned MDA, the MDA is the RAA.
5. Any requirements related to Enterprise Data Management or Information Technology (IT) Services must be coordinated with the Chief
Technology and Innovation Officer (CTIO) prior to approval per the CSO’s Delegation of Requirements Decision Authority (RDA) Memo
dated 9 November 2022.
3.3. Requirement Review and Documentation. A RAD in the form of a memorandum and/or
an electronic approval record is mandatory for all services acquisitions applicable to this DAFI,
unless otherwise exempted (see Chapter 1) or validated by other means (see paragraph 3.2.3.).
Organizations may mandate the use of the Requirements Application of AFPEO/CM’s Strategic
Management Tool (SMT) to facilitate the review, approval, and documentation of services
requirements.
DAFI63-138 2 JANUARY 2024 23
3.3.1. The requiring activity shall assess, review, and validate the following as part of the
requirement approval process:
3.3.1.1. Mission Need. Explanation of the need for the requirement and the outcomes to
be achieved by the services acquisition. (T-1) Exception: S-PEO/TEO (T-3)
3.3.1.2. Strategic Alignment. How the requirement supports the overall organizational
mission and the interests of the DAF. (T-1) Exception: S-PEO/TEO (T-3)
3.3.1.3. Workforce Analysis. Analysis of the decision to contract for services from a
manpower perspective, taking into consideration total force management policies and
procedures. (T-1) Exception: S-PEO/TEO (T-3)
3.3.1.4. Relationship to Other Requirements. How the requirement may impact other
requirements or vice versa. (T-1) Exception: S-PEO/TEO (T-3)
3.3.1.5. Projected Cost of Requirement. Estimated cost of fulfilling the requirement for
the projected total period of performance including options and extensions. (T-1)
Exception: S-PEO/TEO (T-3)
3.3.1.6. Contract and Work Functions. Review requirement for inherently governmental
functions, closely associated with inherently governmental functions, or critical functions.
(T-1) Exception: S-PEO/TEO (T-3)
3.3.2. The RAD, regardless of form, at a minimum shall document the following information:
3.3.2.1. A description of the requirement, anticipated service start date, the need for the
requirement, and the outcomes to be achieved. (T-1) Exception: S-PEO/TEO (T-3)
3.3.2.2. A description of how the requirement was previously satisfied and/or what
changed in the environment to require the need for a contracted solution, if applicable.
Include a description of the nature and extent of market research conducted. (T-1)
Exception: S-PEO/TEO (T-3)
3.3.2.3. The impact to the mission if the RAD is not approved. (T-1) Exception: S-
PEO/TEO (T-3)
3.3.2.4. An estimate of the total cost of the potential program including all
periods, options, and extensions. (T-1) Exception: S-PEO/TEO (T-3)
3.4. Other RAD Considerations.
3.4.1. A RAD is required before a DAF organization may establish an inter-agency agreement
to fund a requirement. (T-1)
3.4.2. A blanket RAD is a requirements approval that spans multiple requirements of a similar
nature for a program or over the life of a contract vehicle ordering period.
3.4.3. RADs for strategic contract vehicles (non-DAF). When using another agency's
enterprise contract vehicle with decentralized ordering, an appropriately approved DAF RAD,
or DAF-approved blanket RAD, is required. (T-1)
3.4.4. RADs for strategic contract vehicles (DAF). For a DAF contract vehicle with
decentralized ordering, an appropriately approved DAF RAD, or DAF-approved blanket RAD,
is required for the award of the basic contract executed by the procuring organization. (T-1)
24 DAFI63-138 2 JANUARY 2024
RAD amount will be for the entire ceiling value based on anticipated users. A separate RAD
must be executed for task orders not included in the original contract RAD value. (T-1)
3.4.5. If the funding agency and the requiring activity are different, the RAD processing shall
follow the processes and procedures established by the requiring activity’s management
structure. The RAD shall be coordinated through the funding agency prior to approval.
Requirement approval is not dependent on funding availability. (T-1)
3.4.5.1. Installation and Mission Support service requirements ≥$10M that are resourced
by Air Force Installation and Mission Support Center (AFIMSC) and wholly funded
through Operating Agency Codes (OAC)-18 account elements shall be approved by the
appropriate AFIMSC authority, regardless of the MAJCOM/FLDCOM executing the
requirement. (T-2) The requirement shall be assessed, reviewed, and validated by the
owning MAJCOM/FLDCOM before AFIMSC approval. Owning MAJCOM/FLDCOM
must coordinate on the RAD prior to AFIMSC approval. (T-2)
3.4.5.2. Requirements ≥$10M that are partially funded by OAC-18 account elements shall
follow the respective MAJCOM/FLDCOM’s requirement approval process. RAD shall
also be coordinated with AFIMSC. (T-2)
3.4.5.3. AFIMSC approval authorities are defined by the MAJCOM/FLDCOM RAA
structure (see Tables 3.1 and 3.2.), Air Force Materiel Command SMA, and further written
delegations.
3.5. Acquisitions with Different Execution and Funding Organizations.
3.5.1. DAF requirements executed by a non-DAF entity, to include Assisted Acquisitions,
require an approved RAD. Non-DAF requirements executed by a DAF entity require
documented evidence of requirement approval. Non-DAF requirement approval may follow
the processes and procedures established by the non-DAF organization. (T-1) Exception: S-
PEO/TEO (T-3)
3.5.2. If an acquisition solution to use a non-DAF procuring office to satisfy customer
requirements is determined to be in the best interest of the DAF, the requiring activity
representative or the assigned PM/SAL shall submit a RAD (approved by the RAA) (see para
3.4.1). (T-1) The approved RAD along with a SADA memorandum approving the use of a
non-DAF procuring office must be included with any applicable Military Interdepartmental
Purchase Request (MIPR) package. Organizations may use their own format for the SADA
memo.
3.5.3. When a DAF entity serves as the procuring organization for a non-DAF entity, the
procuring organization shall obtain a copy of a signed host tenant support agreement or MOA.
The agreement must reflect the current environment of the scope of requirements or number
of resources available to support procurement of the requirement and contract administration
for the life of the contract vehicle. (T-2) If the agreement does not reflect the current
environment of the scope of requirements or number of resources available to support, then
the principal parties shall revisit the agreement. (T-2) If no host tenant support agreement or
MOA exists, an agreement shall be written which acknowledges an awareness of the
requirement and that the procuring organization has both the willingness and adequate
personnel to support procurement of the requirement. (T-2) See AFI 25-201 and DoDI
4000.19, Support Agreements, for more information.
DAFI63-138 2 JANUARY 2024 25
3.6. Amended Requirements.
3.6.1. An amended RAD is required when the value of the approved service exceeds the
approval authority of the RAA who approved the initial RAD. Include the initial RAD in the
amended RAD approval package. (T-1) Exception: S-PEO/TEO (T-3)
3.6.2. When the value of the acquisition exceeds 25% of the approved RAD but does not
exceed the approval authority of the RAA, the PM/SAL shall inform both the SADA and the
RAA of the value increase in writing. (T-1) Exception: S-PEO/TEO (T-3)
3.6.3. When there are changes to the scope of the original requirement that were not
contemplated when the initial RAD was approved, the initial RAD will be canceled and a
new RAD must be processed for the entire requirement. (T-1) Exception: S-PEO/TEO (T-3)
26 DAFI63-138 2 JANUARY 2024
Chapter 4
SERVICES ACQUISITION PROCESS
4.1. Overview. The Services Acquisition Process starts when an organization identifies a mission
requirement that can best be satisfied by contract and acquisition objectives defined by the
requiring activity. Acquisition success depends largely on the preparation and planning conducted
by the MFT prior to solicitation and award. The PM/SAL leads the MFT through the Seven Steps
to the Services Acquisition Process to ensure proven, repeatable processes and procedures as
described in DoDI 5000.74. The seven steps should be implemented in a manner consistent with
the complexity and dollar value of an acquisition. Acquisition planning, market and enterprise
research, and risk assessment, shall occur early and continuously throughout the acquisition
process. The MFT is responsible for assessing, documenting, measuring, and reporting post-award
service provider performance. Organizations may mandate the use of the Services Acquisitions
application of AFPEO/CM’s SMT to create, manage, and track the services acquisition and
contract information. Additional information on the Seven Steps to the Services Acquisition
Process may be found on the AFPEO/CM SharePoint website. (see References in Attachment 1)
4.2. Acquisition Planning (Steps 1 and 2). The MFT (led by the PM/SAL) shall complete
acquisition planning activities to include forming the team, developing a team charter (see
paragraph 2.11.3), defining the scope of the requirement with the requiring activity, establishing
schedule, assessing past strategies and their effectiveness, assessing current performance (if
reacquiring services), identifying stakeholders, and conducting a risk assessment. (T-1) Services
acquisition planning and coordination activities shall allow sufficient time to develop or re-validate
services requirements consistent with the requiring activity stated objectives.
4.2.1. Metrics. MFTs shall employ performance management metrics to achieve efficiencies
in procurement of services using performance-based services contracting, competition,
program review spend analyses, and improved management of services contracts. MFTs
should tailor specific metrics to the needs of the requiring activity. Metrics must track and
measure performance effectively, support and inform acquisition planning, and be considered
during the requirement review and approval process.
4.2.2. Services Acquisition Workshop (SAW). See DoDI 5000.74 for MFT requirement to
participate in a SAW provided by DAU. The DAF SSM waives the specific SAW requirement
for all task orders greater than or equal to $100M and less than $500M unless the acquisition
is determined special interest.
4.2.3. Assisted Acquisitions. The use of an assisted acquisition to satisfy a requirement may
also be introduced during the acquisition planning phase. When an assisted acquisition solution
is determined by the MFT to be the best approach, seek SADA approval in writing. Personnel
from the assisting organization will participate in all pre-award and post-award phases of the
acquisition according to their defined roles. Any authorities being delegated to an outside
agency shall be delegated in writing. (T-1) Assisted acquisitions require a Fiscal Service (FS)
Form 7600A, Agreement Between Federal Program Agencies for Intragovernmental
Reimbursable, Buy/Sell Activity, detailing the roles and responsibilities of the requesting office
and supporting acquisition office. An MOA may be used to further detail terms and conditions
in addition to the FS Form 7600A. Recommend use of an MOA for DAF intra-agency
DAFI63-138 2 JANUARY 2024 27
acquisitions. Adhere to AFI 65-118 for all assisted acquisitions that require acquisition support
outside of the DAF.
4.3. Market and Enterprise Research (Step 3). MFTs shall follow the market research policies
and procedures in FAR Part 10, Market Research. (T-0) When executing a new or follow-on
strategic/enterprise vehicle, market research will likely require more in-depth assessments of the
marketplace, including DAF’s enterprise leverage, potential industry partners, and how to align
with commercial best practices. MFTs shall engage with industry early and often to inform
acquisition strategies that maximize competition, consider opportunities for small business and
AbilityOne non-profit agency (see FAR 8.705-1, Procedures) participation, and increase reliance
on commercial capabilities and technologies. MFTs shall consider strategic sourcing and use of
enterprise vehicles, such as pre-existing contracts (inter- and intra-agency contracts), to fulfill
services requirements before awarding new contracts (see FAR 7.102(a)(4), Policy). (T-0)
4.4. Early Strategy and Issues Session (ESIS). The purpose of an ESIS is to facilitate a candid
and collaborative working session to discuss ideas, best practices, and significant acquisition
issues. An ESIS is not meant to establish an acquisition strategy or to solicit a decision but serves
as a vector-check from senior leaders prior to solidifying the acquisition strategy. The MFT should
formally document any direction provided by the SADA for the acquisition. An ESIS is mandatory
for all services acquisitions greater than or equal to $100M and is recommended for services
acquisitions below $100M. (T-1)
4.4.1. ESIS participants from the MFT include the requiring activity representative, SADA,
PM/SAL, contracting personnel, and other relevant MFT members (e.g., current COR (follow-
on requirements), prospective COR (new requirements), financial management (FM), small
business (SB), legal, security, manpower, safety).
4.4.2. When establishing milestones, schedule the ESIS after preliminary market research is
conducted and no later than 90 calendar days prior to the ASP. (T-3) SADAs may approve
earlier ASP briefings.
4.4.3. Consider holding a follow-on ESIS if market research or other considerations lead the
team in a new direction that is more advantageous for the acquisition. If a follow-on ESIS is
not feasible, discuss post-ESIS changes during the ASP briefing.
4.5. Requirements Definition (Step 4). MFTs shall align services requirements with the stated
requiring activity objectives. Requirements shall be written in a performance-based manner
supporting measurable cost, schedule, and performance outcomes tied to service quality and
delivery. Integrate the results of risk analysis to assist in shaping the performance-based
requirements. Performance-based requirements provide industry flexibility in meeting services
requirements while relying on industry best practices and standards, where possible. Requirements
shall be stated in terms of what is to be accomplished (result), rather than how to accomplish the
work (method). Requiring activity representatives shall ensure that any citation to an instruction
or directive within a performance work statement (PWS) is specific and does not reference the
entire publication. The CO should share draft PWSs with industry for review and feedback.
4.5.1. The Quality Assurance Surveillance Plan (QASP) measures a contractor’s performance
against PWS requirements. See Chapter 6 for Quality Oversight.
4.5.2. MFTs shall develop an Independent Government Cost Estimate (IGCE) to be submitted
with the requirement package to Contracting. An IGCE is the Government’s estimate of the
28 DAFI63-138 2 JANUARY 2024
contractor’s projected price for the successful performance of the contract. IGCE format and
contents will vary depending on the complexity and value of the requirement and cost
estimating technique employed, such as analogous, parametric, and bottom-up. IGCEs should
be treated as Controlled Unclassified Information (CUI). Accurate IGCEs are critical for use
in source selections, sole source negotiations, budget planning, and future requirement
changes. Common elements of costs found in an IGCE include labor skill mix, hours, direct
and indirect costs based on service levels, frequency of performance, and quality levels.
4.5.3. The PM/SAL is responsible for leading the development and coordination of
requirements with functional SMEs.
4.5.3.1. Representatives from all applicable functional disciplines will support the
PM/SAL in defining the requirement.
4.5.3.2. The PM/SAL shall include applicable safety, security, intelligence supportability,
statutory, and regulatory requirements associated with contracted services as appropriate.
Specific instructions that must be reviewed with airworthiness and safety SMEs are:
4.5.3.2.1. DAFI 62-601, Airworthiness. As applicable, include airworthiness
requirements in the PWS. (T-1)
4.5.3.2.2. Defense Contract Management Agency Instruction 8210.1, Contractor’s
Flight and Ground Operations. As applicable, include flight and ground safety
Contractor-Owned, Contractor Operated air services requirements in the PWS. (T-1)
4.5.3.2.3. AFI 91-202, The US Air Force Mishap Prevention Program. As applicable,
include safety reviews/processes, systems safety and safety risk assessments and
acceptance, in the PWS. (T-1)
4.5.3.2.4. DAFI 91-204, Safety Investigations and Reports. As applicable, include
mishap investigation and reporting responsibilities in the PWS. (T-1)
4.5.3.2.5. AFI 63-101/20-101, paragraph 4.16.. As applicable, include critical
intelligence supportability requirements in the PWS. (T-1)
4.6. Acquisition Strategy (Step 5).
4.6.1. Ensure the services acquisition strategy aligns with mission objectives and establishes
a methodology that optimizes and drives performance. The selected contract type, source
selection procedures, and contract incentives (if used) shall align to stated requirements and
objectives. Consider applicable fees when contemplating use of inter-agency vehicles. Non-
performance based requirements and strategies shall be approved by the SADA (see
paragraph 2.5.2.). Organizations shall use templates established by AFPEO/CM for briefings
identified below (see References in Attachment 1). All templates are tailorable to specific
organizational acquisitions. The assigned AFPEO/CM Program Director shall be invited to
attend all ESIS and ASP briefings for services acquisitions greater than or equal to $100M.
4.6.2. Acquisition Plan (AP) and Acquisition Strategy Panel (ASP). The acquisition strategy
shall be documented in a comprehensive, integrated acquisition plan covering all cost,
schedule, technical, business, and support strategies to manage program risks and meet
program objectives. (T-0) Develop evaluation criteria that allow the Government to make
meaningful differentiations among proposals ensuring consistency and linkage between the
PWS and the finalized solicitation. DFARS 207.103 determines when a written AP is required.
DAFI63-138 2 JANUARY 2024 29
Prepare the AP as described in FAR 7.105, DFARS 207.105, and DAFFARS 5307.105,
Contents of Written Acquisition Plans, and DAFFARS 5307.104-92. ASP briefing charts
satisfy the requirement for a written AP only when they satisfy the requirements of FAR 7.105
and DFARS 207.105.
4.7. Execute Acquisition Strategy (Step 6). The acquisition strategy is executed by the MFT.
The strategy may include a variety of approaches to meet mission requirements. Acquisitions may
be competitive or non-competitive in nature. In either case, the MFT shall follow the applicable
business and contract clearance procedures defined in DAFFARS 5301.90, Clearance. (T-0)
Competitive acquisition strategies are preferred. When necessary to procure through non-
competitive means, see FAR 6, Competition Requirements. When execution will be accomplished
using a competitive source selection process, the acquisition will be accomplished as described in
FAR 15.3, Source Selection, the Department of Defense Source Selection Procedures, and
DAFFARS MP 5315.3, Source Selection. (T-0)
4.8. Post-Award Performance Management (Step 7).
4.8.1. This step ensures effective management of cost, schedule, performance, and risk after
contract award. The PM/SAL will ensure continued participation by the MFT during contract
administration. The CO and PM/SAL should conduct a post-award conference (kick-off
meeting) with the MFT and the contractor team members to ensure a common understanding
of services requirements, expectations, and responsibilities of all members. The PM/SAL shall
manage the transition plan timeline and monitor activities to ensure a smooth contract
transition. (T-1) See FAR 42.5, Post-award Orientation.
4.8.2. The PM/SAL and the MFT shall implement services post-award management processes
and tools that will be used to ensure successful execution in terms of cost, schedule,
performance, and risk. (T-0) At a minimum, services post-award management will address the
following:
4.8.2.1. Program objectives and goals aligned to those of senior leaders and the mission
with associated metrics to measure and track success of the program.
4.8.2.2. A process for contract modifications.
4.8.2.3. Management of Government-Furnished Property, if applicable.
4.8.2.4. Tracking, reviewing, and analyzing contract deliverables, data, and data markings.
4.8.2.5. Management of risk, issues, and opportunities.
4.8.2.6. Obtaining, allocating, and prioritizing funding.
4.8.2.7. Timely review and acceptance of invoices for services received.
4.8.2.8. Contractor performance assessment, documentation, and reporting to include
development and submission of the CPAR.
4.8.2.9. Program Management Reviews (PMRs) with the contractor, requiring activity,
and other key stakeholders to review cost, schedule, performance, risks, issues, and
opportunities.
4.8.2.9.1. Conduct PMRs for all S-CAT I, II, and III programs with the organization’s
senior leadership and key stakeholders on at least an annual basis. (T-1) These PMRs
30 DAFI63-138 2 JANUARY 2024
are separate from the AFPEO/CM AERs and Effectiveness Reviews. Consider PMRs
for S-CAT IV and V programs based on the scope, complexity, and mission of the
contracted service. Organizations may use their own PMR format. The designated
AFPEO/CM Program Director shall be invited to all PMRs for programs (not assigned
to S-PEOs/TEOs) with a program value greater than or equal to $100M. (T-1)
4.8.2.9.2. Collect cost, schedule, and performance data to effectively manage the
program.
4.8.2.9.3. Use performance management metrics as part of PMRs to review cost,
schedule, performance, risks, issues, and opportunities associated with current
contractual performance.
4.8.2.9.4. When discovered, report significant impacts to cost, schedule, or
performance through the leadership chain to the SADA with a plan of action for
resolution.
DAFI63-138 2 JANUARY 2024 31
Chapter 5
GOVERNANCE ASSESSMENT
5.1. Governance Assessment. An annual review of services acquisition programs and processes
is required for all organizational structures within the DAF (see DoDI 5000.74 para 4.6a). The
assessment consists of an Annual Execution Review (AER) on programs greater than or equal to
$100M and an overall self-assessment of the organization’s governance of all services over the
SAT (Effectiveness Review). The governance assessment briefings cover the previous fiscal year’s
services acquisitions and conclude no later than 15 March of the current fiscal year. (T-1)
Organizations shall use templates established by AFPEO/CM for the briefings (see link for
AFPEO/CM SharePoint website located in References in Attachment 1). (T-1) Organizations
will develop and implement internal policies and procedures to evaluate programs greater than or
equal to the SAT and less than $100M. (T-1) Organizations using both the Requirements and
Services Acquisition applications of SMT may use SMT’s Services Review and Enterprise
Analytics applications to generate their governance assessment briefings.
5.2. Applicable to Secretariat, Air Staff, and Space Staff.
5.2.1. Deputy Under Secretary of the Air Force (Management) (SAF/MG) is the designated
Secretariat and Air Staff Services Advocate responsible for the governance assessment. Space
Force Director of Staff (SF/DS) is the designated Space Staff Services Advocate responsible
for the governance assessment.
5.2.2. Annual Execution Reviews (AERs). The AER assesses cost, schedule, performance,
risks, and issues of individual programs.
5.2.2.1. Organizations shall complete AERs for all programs greater than or equal to
$100M, including those executed by non-DAF entities (e.g., General Services
Administration, Defense Information Systems Agency). (T-1)
5.2.2.2. PMs/SALs shall brief their respective programs. (T-1)
5.2.2.3. SAF/MG and SF/DS should consider inclusion of programs under $100M based
on risk, complexity, and performance.
5.2.3. Effectiveness Review. This review encompasses a self-assessment of the organization’s
ability to manage and govern services in the areas of People, Process, and Performance for
those requirements greater than or equal to the SAT. (T-1)
5.3. Applicable to MAJCOMs, FLDCOMs, FOAs, and DRUs.
5.3.1. The organizational SADA may delegate responsibility for the governance assessment
to the SA.
5.3.2. Annual Execution Reviews (AERs). The AER assesses cost, schedule, performance,
risks, and issues of individual programs.
5.3.2.1. Organizations shall complete AERs for all programs greater than or equal to
$100M including those executed by non-DAF entities (e.g., General Services
Administration, Defense Information Systems Agency). (T-1)
5.3.2.2. PMs/SALs shall brief their respective programs. (T-1)
32 DAFI63-138 2 JANUARY 2024
5.3.2.3. The SA should consider inclusion of programs under $100M based on risk,
complexity, and performance. AFPEO/CM may specifically request briefings for select
programs under $100M.
5.3.3. Effectiveness Review. This review encompasses a self-assessment of the organization’s
ability to manage and govern services in the areas of People, Process, and Performance for
those requirements greater than or equal to the SAT. See paragraph 2.8.4 for Effectiveness
Review roles and responsibilities. (T-1)
5.4. Applicable to Systems PEOs/TEOs.
5.4.1. The S-PEO/TEO is the SADA for services acquisitions.
5.4.2. Following the end of each fiscal year, S-PEOs/TEOs shall conduct an annual review of
their services requirements, i.e., a Services Requirements Review (see paragraph 2.7.3). (T-1)
This annual review is briefed to the cognizant SAE and provides an effective overview of the
management, performance, and governance of services acquisitions within each S-PEO/TEO
portfolio. Use the template provided on the AFPEO/CM SharePoint website (see References
in Attachment 1). (T-1) SAF/AQ and SAF/SQ consolidate the inputs from their respective S-
PEOs/TEOs into integrated Health of Services assessments for the S-PEO/TEO structure.
5.5. Annual Summary. AFPEO/CM creates an annual integrated assessment for DAF services
programs within their portfolio. (T-1) The integrated assessment is provided to the Services
Review Group (SRG) no later than 30 April.
5.5.1. The SRG is a three-star level panel which consists of principals from
SAF/Administrative Assistant (AA), AF/Director of Staff (DS), SF/DS, and SAF/MG.
5.5.2. The SRG reviews the information to identify DAF-wide synergies, efficiencies, and
strategic opportunities. The SRG’s recommendations may be presented to the DAF Council.
DAFI63-138 2 JANUARY 2024 33
Chapter 6
QUALITY OVERSIGHT
6.1. Overview. The Government’s role in quality oversight is to ensure it receives the services
contracted for and only pays for the services received. The Government’s approach to quality is
documented in the Quality Assurance Surveillance Plan (QASP). The type and extent of contract
quality requirements needed depends on the service being acquired (see FAR 46.201, Contract
Quality Requirement, General). Solicitations and contracts may provide for alternative, but
substantially equivalent, inspection methods to obtain wide competition and low cost. However,
the CO may authorize contractor recommended inspection alternatives when in the Government's
interest and approved by the requiring activity. Quality is the responsibility of the services
contractor, not the Government. A guiding principle to quality is that the COR’s level of
surveillance is commensurate with the level of risk associated with contractor performance.
6.1.1. Contract quality requirements for services above the SAT fall into three general
categories, depending on the extent of quality assurance needed by the Government for the
acquisition.
6.1.1.1. Contracts for commercial services. The Government shall rely on the contractor
to accomplish all inspection and testing needed to ensure that commercial services acquired
conform to contract requirements before they are tendered to the Government (see clause
at FAR 52.212-4, Contract Terms and ConditionsCommercial Products and
Commercial Services).
6.1.1.2. Standard inspection requirements. Contractors provide an acceptable inspections
system, give the Government the right to inspect, and keep complete records of inspection
work. Services related clauses include FAR 52.246-4, Inspection of Services-Fixed-Price;
FAR 52.246-5, Inspection of Services-Cost Reimbursement; and 52.246-6, Inspection-
Time-and-Material and Labor-Hour.
6.1.1.3. Higher-level contract quality requirements. Requiring higher-level quality
standards may be necessary in solicitations and contracts for complex or critical services
(see FAR 46.202-4, Higher-Level Contract Quality Requirements, and clause at FAR
52.246-11, Higher-Level Contract Quality Requirement). Higher-level contract quality
requirements are used in addition to standard inspection requirement (see DFARS 246.202-
4, Higher-Level Contract Quality Requirements).
6.1.2. Background. Sections 4501, 4502, and 4505 of Title 10, United States Code (USC)
mandate Performance-Based Services Acquisition goals, cost savings, and a
management/oversight structure for services acquisitions similar to the procurement of
products.
6.1.3. Additional Information. The MFT Resources Guide on the AFPEO/CM SharePoint site
(see References in Attachment 1) provides greater detail and best practices for quality
oversight information and MFT roles and responsibilities.
6.2. Quality Assurance Surveillance Plan (QASP).
6.2.1. Purpose. The purpose of a QASP is to provide a documented process for surveilling the
contractor's actual performance and comparing that to the technical requirements of the
34 DAFI63-138 2 JANUARY 2024
contract. The QASP identifies and describes the roles and responsibilities for implementing
and maintaining the key elements of contract performance management and surveillance.
6.2.2. QASP Development. The QASP is developed based on the surveillance necessary to
assess contractor compliance to PWS requirements. Mission essential/critical Services
Summary (SS) items with measurable performance thresholds shall be included in the PWS.
The MFT ensures the QASP includes the SS items with performance objectives (acceptable
quality levels), surveillance methods, and surveillance frequency. Other PWS/contract items
are included within the QASP for surveillance, on an as needed basis, to ensure PWS coverage.
Furthermore, the QASP identifies how CORs link surveillance of SS items to periodic
surveillance reporting and to CPARS reporting. The QASP may be shared with the contractor
to provide transparency regarding the Government’s surveillance methodology but shall not
be part of the resulting contract.
6.2.3. QASP Related Requirements: QASP-related requirements are addressed in several
regulatory, procedural, instructional, and guidance documents. These documents should be
consulted for each acquisition to determine an appropriate QASP approach. Consult FAR Parts
12, Acquisition of Commercial Products and Commercial Services, 37, Service Contracting,
and 46, Quality Assurance; DFARS 237.172, Service contracts surveillance, and 246.401,
Government Contract Quality Assurance; DFARS PGIs 222.1703(4), Combating Trafficking
In Persons, Policy, and 237.172, Service contracts surveillance; DAFFARS MP 5301.602-
2(d) and 5346.103; the MFT Resources Guide on the AFPEO/CM SharePoint site; and any
applicable functional community guidance (e.g., DAFI 21-101, Aircraft and Equipment
Maintenance Management, for aircraft maintenance community) for QASP requirements. This
is not an all-inclusive list.
6.2.4. DoD has mandated use of the Joint Appointment Module (JAM) and the Surveillance
and Performance Monitoring Module (SPM) within the Procurement Integrated Enterprise
Environment (PIEE) system for all contracts for which a COR has been designated. (T-0) See
DoDI 5000.72 for further information.
6.3. Actions to Address Substandard Services and Contractual Non-Conformities. The types
of corrective actions available to the Government for contractor services not meeting contract
requirements will be prescribed in the contract. When developing the solicitation, the MFT shall
carefully consider which contract terms, conditions, and clauses should be included in the contract
to allow substandard service and non-conformities to be appropriately addressed. (T-2)
Exception: S-PEO/TEO (T-3)
ANDREW P. HUNTER
Assistant Secretary of the Air Force
(Acquisition, Technology & Logistics)
DAFI63-138 2 JANUARY 2024 35
Attachment 1
GLOSSARY OF REFERENCES AND SUPPORTING INFORMATION
References
10 USC § 4501, Procurement of contract services: management structure
10 USC § 4502, Procurement of contract services: senior officials responsible for management
of acquisition of contract services
10 USC § 4505, Procurement of services: tracking of purchases
DoDI 4000.19, Support Agreements, 16 December 2020
DoDI 5000.02, Operation of the Adaptive Acquisition Framework, 23 January 2020
DoDI 5000.66, Defense Acquisition Workforce Education, Training, Experience, and Career
Development Program, 27 July 2017
DoDI 5000.72, DoD Standard for Contracting Officer’s Representative (COR) Certification, 26
March 2015
DoDI 5000.74, Defense Acquisition of Services, 10 January 2020
DoDI 5000.77, DoD Federally Funded Research and Development Center (FFRDC) Program,
31 January 2018
DoDD 5100.03, Support of the Headquarters of Combatant and Subordinate Unified Commands,
09 February 2011
AFPD 63-1/20-1, Integrated Life Cycle Management, 7 August 2018
DAFI 21-101, Aircraft and Equipment Maintenance Management, 16 January 2020
AFI 25-201, Intra-Service, Intra-Agency, and Inter-Agency Support Agreement Procedures, 18
October 2013
AFI 33-322, Records Management and Information Governance Program, 28 July 2021
DAFI 62-601, Airworthiness, 10 June 2022
AFI 63-101/20-101, Integrated Life Cycle Management, 30 June 2020
AFI 65-118, AF Purchases Using Military Interdepartmental Purchase Requests (MIPRS), 8
April 2020
DAFI 91-202, The US Air Force Mishap Prevention Program, 12 March 2020
DAFI 91-204, Safety Investigations and Reports, 10 March 2021
AFMAN 63-122, Depot Source of Repair Planning and Activation, 21 January 2020
DAFMAN 90-161, Publishing Processes and Procedures, 18 October 2023
Federal Acquisition Regulation (FAR)
Defense Federal Acquisition Regulation Supplement (DFARS)
Department of the Air Force Federal Acquisition Regulation Supplement (DAFFARS)
36 DAFI63-138 2 JANUARY 2024
Department of Defense Contracting Officer’s Representatives Guidebook, October 2022
Department of Defense Source Selection Procedures, 20 August 2022
Air Force Installation and Mission Support Center (AFIMSC) Standard Process for Contract
Support Services (CSS) Requirements Approval, August 2021
AFPEO/CM SharePoint website:
https://usaf.dps.mil/sites/SAFAQ/projects/services/sitepages/peocm.aspx
Prescribed Forms
None
Adopted Forms
DAF Form 847, Recommendation for Change of Publication
FS Form 7600A, Agreement Between Federal Program Agencies for Intragovernmental
Reimbursable, Buy/Sell Activity
Abbreviations and Acronyms
AERAnnual Execution Review
AFIAir Force Instruction
AFIMSCAir Force Installation and Mission Support Center
AFPDAir Force Policy Directive
ANGAir National Guard
APAcquisition Plan
ASPAcquisition Strategy Panel
A&ASAdvisory and Assistance Services
CAExecutive Director
CCCommander
CDDeputy Commander
C-COR—Chief, Contracting Officer’s Representative
COContracting Officer
COR—Contracting Officer’s Representative
CORT—Contracting Officer’s Representative Tracking
CPARContract Performance Assessment Report
CPARSContract Performance Assessment Reporting System
CUIControlled Unclassified Information
CVVice Commander
DAFI63-138 2 JANUARY 2024 37
DAFDepartment of the Air Force
DAFFARSDepartment of the Air Force Federal Acquisition Regulation Supplement
DAFIDepartment of the Air Force Instruction
DAUDefense Acquisition University
DAWIADefense Acquisition Workforce Improvement Act
DCMADefense Contract Management Agency
DFARSDefense Federal Acquisition Regulation Supplement
DoDDepartment of Defense
DoDIDepartment of Defense Instruction
DRUDirect Reporting Unit
DSDirector of Staff
ESISEarly Strategy and Issues Session
FARFederal Acquisition Regulation
FFRDCFederally Funded Research and Development Center
FLDCOMField Command
FMFinancial Management
FMSForeign Military Sales
FOAField Operating Agency
FSFiscal Service
FSMFunctional Services Manager
GO/SESGeneral Officer/Senior Executive Service
HAFHeadquarters Air Force (Composed of Secretariat, Air Staff, and Space Staff)
IGCEIndependent Government Cost Estimate
JAMJoint Appointment Module
MAJCOMMajor Command
MDAMilestone Decision Authority
MFTMulti-Functional Team
MIPRMilitary Interdepartmental Purchase Request
MLMateriel Leader
MOAMemorandum of Agreement
MPMandatory Procedure
OACOperating Agency Codes
38 DAFI63-138 2 JANUARY 2024
OCSOOffice of the Chief of Space Operations
OSDOffice of the Secretary of Defense
PEOProgram Executive Officer
PGIProcedures, Guidance, and Information
PIEEProcurement Integrated Enterprise Environment
PMProgram Manager
PMRProgram Management Review
PWSPerformance Work Statement
QAPCQuality Assurance Program Coordinator
QASPQuality Assurance Surveillance Plan
RAARequirements Approval Authority
RADRequirements Approval Document
SAServices Advocate
SADAServices Acquisition Decision Authority
SAEService Acquisition Executive
SALServices Acquisition Lead
SATSimplified Acquisition Threshold
SAWServices Acquisition Workshop
SBSmall Business
S-CATServices Category
SDOServices Designated Official
SMAServices Management Agreement
SMESubject Matter Expert
SMLSenior Materiel Leader
SMTStrategic Management Tool
S-PEOSystems Program Executive Officer
SPMSurveillance and Performance Monitoring Module
SRRServices Requirements Review
SRRBServices Requirements Review Board
SSServices Summary
SSASource Selection Authority
SSMSenior Services Manager
DAFI63-138 2 JANUARY 2024 39
TEOTechnology Executive Officer
USecAFUnder Secretary of the Air Force
USSFUnited States Space Force
VCSAFVice Chief of Staff of the Air Force
VCSOVice Chief of Space Operations
Office Symbols
AFPEO/CMAir Force Program Executive Officer for Combat and Mission Support
SAF/AAAdministrative Assistant to the Secretary of the Air Force
SAF/AQAssistant Secretary of the Air Force (Acquisition, Technology, & Logistics)
SAF/MGDeputy Under Secretary of the Air Force (Management)
SAF/SQAssistant Secretary of the Air Force (Space Acquisition and Integration)
SF/DSSpace Force Director of Staff
USD(A&S)Under Secretary of Defense for Acquisition and Sustainment
Terms
Acquisition PlanA formal written document reflecting the specific actions necessary to execute
the approach established in the approved Acquisition Strategy Panel and guiding contractual
implementation.
Acquisition Strategy Panel (ASP)An ASP includes the Chair, panel members, and a briefing
supporting the proposed strategy. The ASP briefing is presented to the acquisition plan approving
authority (SADA, unless delegated) to allow discussion of the proposed strategy and promote an
informed decision.
Annual Execution Review (AER)An annual review of services acquisition programs which
assesses cost, schedule, and performance of individual programs. Presented to AFPEO/CM by the
Program Manager or the Services Acquisition Lead of each program.
Assisted AcquisitionA type of interagency acquisition where a servicing agency performs
acquisition activities on a requesting agency's behalf, such as awarding and administering a
contract, task order, or delivery order.
Direct Reporting UnitA subdivision of the Air Force, directly subordinate to the Chief of Staff,
US Air Force. A DRU performs a mission that does not fit into any of the MAJCOMs.
Early Strategy and Issues SessionA candid and collaborative working session held early in
the acquisition process to discuss ideas, best practices, and significant acquisition issues.
Effectiveness ReviewAn annual self-assessment of an organization’s ability to manage and
govern services requirements greater than or equal to the SAT. Typically presented by the
organization’s Services Advocate to AFPEO/CM.
40 DAFI63-138 2 JANUARY 2024
Field Operating AgencyA subdivision of the Air Force, directly subordinate to a HQ USAF
functional manager. A FOA performs field activities beyond the scope of any of the major
commands.
Independent Government Cost EstimateAn estimate of the cost for goods and/or estimate of
services to be procured by contract. Such estimates are prepared by Government personnel, i.e.,
independent of contractors.
Mission Owner/PartnerSee Requiring Activity definition.
Multi-Functional TeamTeam composed of representatives from appropriate functional
disciplines working together and supporting the PM/SAL to create successful acquisition of
services, identify and resolve issues, and make sound and timely recommendations to facilitate
decision-making.
Performance Management MetricsParameters or measures of quantitative assessment used to
track and manage performance. Metrics should be specific, measurable, achievable, relevant, and
timely (SMART).
Program Management ReviewA structured review, conducted by the Program Manager (PM)
or the Services Acquisition Lead (SAL) with all key stakeholders, that assesses and reports
program cost, schedule, performance, risks, issues, and opportunities.
Program ManagerDesignated individual with responsibility for and authority to accomplish
program objectives to meet the needs identified in the acquisition documents. Accountable for
program cost, schedule, and performance and managing their associated risks and issues. Certified
by DAWIA at Practitioner or Advanced level.
Quality Assurance Program CoordinatorThe government individual responsible for
coordinating and managing the Quality Assurance Program.
Quality Assurance Surveillance PlanThe document Government personnel use to assess
contractor performance. The QASP identifies what is going to be inspected, the inspection process,
and who will do the inspecting.
Requirements Approval AuthorityThe individual responsible to identify, assess, validate, and
approve services requirements within Secretariat, Air Staff, Space Staff, MAJCOM, FLDCOM,
DRU, FOA, and S-PEO/TEO organizations.
Requiring ActivityThe organization charged with meeting a mission and delivering
requirements. The requiring activity is responsible for obtaining funding or developing the
program objective memorandum. The requiring activity may also be the organizational unit that
submits a written requirement or statement of need for services required by a contract. The
requiring activity is responsible for delivering the services to meet the mission if a contract is not
in effect. Finally, the requiring activity provides a trained and qualified contracting officer’s
representative capable of determining whether services contract requirements are being performed
following the terms of the contract. This DAFI uses Requiring Activity as an all-encompassing
term for Mission Owner, Mission Partner, Requirements Owner, or Requiring Organization.
Senior Services ManagerThe individual at the general or flag officer or Senior Executive
Service level appointed by the Service Acquisition Executive to be responsible for governance in
planning, execution, strategic sourcing, and management of services acquisitions. The
AFPEO/CM is the designated SSM for the DAF.
DAFI63-138 2 JANUARY 2024 41
Service Acquisition ExecutiveThe civilian official within a military department who is
responsible for the management of acquisition of contract services for or on behalf of that military
department. SAF/AQ serves as SAE for non-space systems and programs. SAF/SQ serves as SAE
for space systems and programs.
Services Acquisition Decision AuthorityThe individual responsible for ensuring a proposed
services acquisition is consistent with DoD and DAF policies, procedures, and best practices
guidelines for the acquisition of services through approval of the acquisition strategy. Formerly
known as the Services Designated Official.
Services Acquisition LeadThe individual from a functional (i.e., requiring) organization who
performs the duties of a Program Manager (see definition above). Individuals in this position are
not DAWIA certified but are expected to attain the DAU Services Acquisition Team Member
Credential.
Services Acquisition ProgramA set of services requirements executed through one or more
contract actions, interagency agreements, and/or other types of acquisitions with a common
mission or objective.
Services AdvocateThe individual who serves as the principal point of contact for services
acquisitions within the Secretariat, Air Staff, Space Staff, MAJCOM, FLDCOM, FOA, or DRU.
Must be GO/SES unless otherwise approved by SSM.
Services Management AgreementDocument between AFPEO/CM and Commander or
Director of the Secretariat, Air Staff, Space Staff, MAJCOM, FLDCOM, FOA, and DRU
organization which identifies the specific organizational roles and responsibilities not contained in
this DAFI. SMAs further define the specific delegations for SADA and RAA within that
organization.
Services Requirements Review BoardThe DAF does not use the term Services Requirements
Review Board (SRRB) as defined in DoDI 5000.74. However, the DAF implements all functions
of an SRRB as described in paragraph 1.1.4.
Services Requirements Review Board ChairThe Requirements Approval Authority (RAA)
performs this function.
Special InterestServices that, by their nature or the circumstances related to their acquisition,
deserve increased attention or care during planning, review, approval, and oversight.
Strategic Management ToolA suite of program management and analysis apps that streamlines
the generation, collection and tracking of services data. The SMT is a DAF enterprise solution that
provides full life-cycle productivity apps from generating a Requirement Approval Document
(RAD) to tracking Pre and Post Award milestones for a Services Acquisition. The Service Review
app provides for automation of program annual review charts.
Systems Program Executive OfficerThe individual dedicated to executive management and
supervision of a portfolio of mission-related programs (both ACAT and S-CAT). The S-PEO
reports directly to the SAE. Formerly referred to as Weapon Systems Program Executive Officer.